Tower bottom anchoring structure of concrete-filled steel tube combined tower and construction method of tower bottom anchoring structure
The invention discloses a tower bottom anchoring structure of a concrete-filled steel tube combined tower and a construction method thereof, and relates to the technical field of bridge construction, the device comprises at least four concrete-filled steel tube tower columns, and the bottoms of the concrete-filled steel tube tower columns are anchored to a concrete foundation; the connecting plate assembly is arranged among the four concrete-filled steel tube tower columns and connected with the four concrete-filled steel tube tower columns, a concrete part is poured in the connecting plate assembly, and the concrete part and the concrete-filled steel tube tower columns are connected into a whole. Compared with the prior art, the connecting plates are adopted to connect the concrete in the tower columns into a whole to share stress, so that the capacity of each tower column for bearing force in all directions is improved, and the durability of the combined tower is improved.
本发明公开了一种钢管混凝土组合塔的塔底锚固结构及其施工方法,涉及桥梁施工技术领域,该装置包括至少四个钢管混凝土塔柱,所述钢管混凝土塔柱底部锚固于混凝土基础;连接板组件,其设于四个所述钢管混凝土塔柱之间,并与四个所述钢管混凝土塔柱相连,所述连接板组件内浇筑有混凝土部,且所述混凝土部与所述钢管混凝土塔柱的连为一体。相比于现有技术,本申请中采用连接板以将多个塔柱内的混凝土连为一体分担受力,从而增加了每个塔柱的承受各向力的能力,进而提高了组合塔的耐久性。
Tower bottom anchoring structure of concrete-filled steel tube combined tower and construction method of tower bottom anchoring structure
The invention discloses a tower bottom anchoring structure of a concrete-filled steel tube combined tower and a construction method thereof, and relates to the technical field of bridge construction, the device comprises at least four concrete-filled steel tube tower columns, and the bottoms of the concrete-filled steel tube tower columns are anchored to a concrete foundation; the connecting plate assembly is arranged among the four concrete-filled steel tube tower columns and connected with the four concrete-filled steel tube tower columns, a concrete part is poured in the connecting plate assembly, and the concrete part and the concrete-filled steel tube tower columns are connected into a whole. Compared with the prior art, the connecting plates are adopted to connect the concrete in the tower columns into a whole to share stress, so that the capacity of each tower column for bearing force in all directions is improved, and the durability of the combined tower is improved.
本发明公开了一种钢管混凝土组合塔的塔底锚固结构及其施工方法,涉及桥梁施工技术领域,该装置包括至少四个钢管混凝土塔柱,所述钢管混凝土塔柱底部锚固于混凝土基础;连接板组件,其设于四个所述钢管混凝土塔柱之间,并与四个所述钢管混凝土塔柱相连,所述连接板组件内浇筑有混凝土部,且所述混凝土部与所述钢管混凝土塔柱的连为一体。相比于现有技术,本申请中采用连接板以将多个塔柱内的混凝土连为一体分担受力,从而增加了每个塔柱的承受各向力的能力,进而提高了组合塔的耐久性。
Tower bottom anchoring structure of concrete-filled steel tube combined tower and construction method of tower bottom anchoring structure
一种钢管混凝土组合塔的塔底锚固结构及其施工方法
LIU KEFENG (Autor:in) / ZOU MINYONG (Autor:in) / SHAN QIUWEI (Autor:in) / MANDA TAMOTSU (Autor:in) / YANG GUANGWU (Autor:in) / LI LIN (Autor:in)
07.03.2023
Patent
Elektronische Ressource
Chinesisch
Cable-stayed bridge steel shell-concrete combined bridge tower cable bent tower anchoring structure
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Novel steel-concrete combined stay cable tower anchoring structure and construction method thereof
Europäisches Patentamt | 2020
|Tower foot anchoring structure for assembling tower and tower building method
Europäisches Patentamt | 2022
|Tower top force transfer structure for concrete filled steel tube combined tower
Europäisches Patentamt | 2024
|