Fabricated construction method for underwater wave-absorbing plates of open-sea open-type breakwater wharf
An open sea open type breakwater wharf underwater wave-absorbing plate assembly type construction method comprises the construction steps that S1, a site around a project is selected, leveled and hardened, a prefabricated wave-absorbing plate concrete bottom tire is manufactured, and a component manufacturing area and a component storage area are arranged; s2, a reinforcing steel bar machining area is planned in a component prefabrication site, and finished concrete piers or steel structure supporting pads are arranged in a reinforcing steel bar and semi-finished product storage area; s3, during prefabricated wave absorbing plate construction, steel bar spacing and layer spacing are guaranteed; s4, prefabricating a wave absorbing plate formwork, and pouring by adopting a horizontal structure; s5, spraying and maintaining the wave absorbing plate; s6, the prefabricated wave absorbing plates are transported to a construction site; s7, mounting the wave absorbing plate; s8, after steel bars and concrete are poured at the secondary joints, the steel bars and the concrete are connected into a whole; and S9, a hoisting point of the prefabricated wave absorbing plate is buried in a horseshoe reserved hole, and secondary ash supplementing and sealing are conducted. The construction process is basically not affected by tide water, the mounting position and elevation control precision is high, the concrete construction quality is ensured, and the structural construction safety risk is reduced.
一种外海透空式防波堤码头水下消波板装配式施工方法,其施工步骤为:S1.选择项目周边场地整平硬化,制作预制消波板砼底胎,设置构件制作区、构件存放区;S2.在构件预制场地规划好的钢筋加工区,并对钢筋及半成品存放区设置成品混凝土墩或钢结构支垫;S3.预制消波板施工时为保证钢筋间距和层距;S4.预制消波板支模、浇筑采用卧式结构;S5.消波板喷淋养护;S6.预制消波板运至施工现场;S7.消波板的安装;S8.二次接缝处钢筋和砼浇筑后连成整体;S9.预制消波板的吊点采用马蹄留孔埋设,二次补灰密封。本发明施工过程基本不受潮水影响,安装位置和标高控制精度高,确保混凝土施工质量,降低结构施工安全风险。
Fabricated construction method for underwater wave-absorbing plates of open-sea open-type breakwater wharf
An open sea open type breakwater wharf underwater wave-absorbing plate assembly type construction method comprises the construction steps that S1, a site around a project is selected, leveled and hardened, a prefabricated wave-absorbing plate concrete bottom tire is manufactured, and a component manufacturing area and a component storage area are arranged; s2, a reinforcing steel bar machining area is planned in a component prefabrication site, and finished concrete piers or steel structure supporting pads are arranged in a reinforcing steel bar and semi-finished product storage area; s3, during prefabricated wave absorbing plate construction, steel bar spacing and layer spacing are guaranteed; s4, prefabricating a wave absorbing plate formwork, and pouring by adopting a horizontal structure; s5, spraying and maintaining the wave absorbing plate; s6, the prefabricated wave absorbing plates are transported to a construction site; s7, mounting the wave absorbing plate; s8, after steel bars and concrete are poured at the secondary joints, the steel bars and the concrete are connected into a whole; and S9, a hoisting point of the prefabricated wave absorbing plate is buried in a horseshoe reserved hole, and secondary ash supplementing and sealing are conducted. The construction process is basically not affected by tide water, the mounting position and elevation control precision is high, the concrete construction quality is ensured, and the structural construction safety risk is reduced.
一种外海透空式防波堤码头水下消波板装配式施工方法,其施工步骤为:S1.选择项目周边场地整平硬化,制作预制消波板砼底胎,设置构件制作区、构件存放区;S2.在构件预制场地规划好的钢筋加工区,并对钢筋及半成品存放区设置成品混凝土墩或钢结构支垫;S3.预制消波板施工时为保证钢筋间距和层距;S4.预制消波板支模、浇筑采用卧式结构;S5.消波板喷淋养护;S6.预制消波板运至施工现场;S7.消波板的安装;S8.二次接缝处钢筋和砼浇筑后连成整体;S9.预制消波板的吊点采用马蹄留孔埋设,二次补灰密封。本发明施工过程基本不受潮水影响,安装位置和标高控制精度高,确保混凝土施工质量,降低结构施工安全风险。
Fabricated construction method for underwater wave-absorbing plates of open-sea open-type breakwater wharf
一种外海透空式防波堤码头水下消波板装配式施工方法
LI XIANGLONG (Autor:in) / SHAO WEI (Autor:in) / XU YANDONG (Autor:in) / ZHANG SHAOKAI (Autor:in) / SONG YIJIAN (Autor:in) / LIU MING (Autor:in) / WANG CHAO (Autor:in) / YANG BIN (Autor:in) / SOMMOU (Autor:in) / XING ZHANLI (Autor:in)
10.03.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
/
B28B
Formgeben von Ton oder anderen keramischen Stoffzusammensetzungen, Schlacke oder von Mischungen, die zementartiges Material enthalten, z.B. Putzmörtel
,
SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
Europäisches Patentamt | 2023
|Prestressed concrete simplifies construction of breakwater/wharf
Engineering Index Backfile | 1969
|Wharf breakwater engineering accropode installation process
Europäisches Patentamt | 2024
|