Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Construction method of large-diameter super-long cast-in-place pile
The invention relates to a large-diameter super-long cast-in-place pile construction method, which relates to the technical field of cast-in-place pile construction technology, and comprises the following steps: a construction preparation step: leveling a construction site, and tamping and filling compactly; a step of embedding a steel pile casing: excavating and embedding the pile casing by adopting a machine; drilling: adopting static slurry to protect the wall in the drilling process; a hole-forming inspection step: when the drilling depth meets the design requirement, inspecting the hole position, the hole diameter, the hole depth, the gradient and the like; a hole cleaning step: cleaning the hole by adopting a slurry changing method; reinforcement cage manufacturing and mounting: pile foundation reinforcement cages are intensively manufactured in a reinforcement yard; the reinforcement cage is mounted by a truck crane; a guide pipe mounting step: hoisting the guide pipe into the hole; secondary hole cleaning, wherein secondary hole cleaning is conducted through the guide pipe; an underwater concrete pouring step, wherein underwater concrete pouring is continuously carried out; and the guide pipe and the steel casing are pulled out, specifically, after underwater concrete pouring is completed, the guide pipe and the steel casing are pulled out slowly through a crane. The cast-in-place pile has the effect of solving the problem that the construction difficulty of the cast-in-place pile is large.
本申请涉及大直径超长灌注桩施工方法,涉及灌注桩施工技术的技术领域,其包括以下步骤:施工准备步骤:平整施工场地,并夯填密实;钢护筒埋设步骤:采用机械开挖埋设护筒;钻孔步骤:钻进过程中采用静态泥浆护壁;成孔检查步骤:当钻孔深度达到设计要求时,对孔位、孔径、孔深和倾斜度等进行检查;清孔步骤:采用换浆法进行清孔;钢筋笼制作安装步骤:桩基钢筋笼在钢筋场中集中制作;钢筋笼安装采用汽车吊;导管安装步骤:导管吊装入孔;二次清孔步骤:利用导管进行二次清孔;灌注水下混凝土步骤:水下混凝土灌注连续进行;拔除导管及钢护筒步骤:水下混凝土灌注完毕,通过吊车慢速拔出。本申请具有改善灌注桩施工时难度大的问题的效果。
Construction method of large-diameter super-long cast-in-place pile
The invention relates to a large-diameter super-long cast-in-place pile construction method, which relates to the technical field of cast-in-place pile construction technology, and comprises the following steps: a construction preparation step: leveling a construction site, and tamping and filling compactly; a step of embedding a steel pile casing: excavating and embedding the pile casing by adopting a machine; drilling: adopting static slurry to protect the wall in the drilling process; a hole-forming inspection step: when the drilling depth meets the design requirement, inspecting the hole position, the hole diameter, the hole depth, the gradient and the like; a hole cleaning step: cleaning the hole by adopting a slurry changing method; reinforcement cage manufacturing and mounting: pile foundation reinforcement cages are intensively manufactured in a reinforcement yard; the reinforcement cage is mounted by a truck crane; a guide pipe mounting step: hoisting the guide pipe into the hole; secondary hole cleaning, wherein secondary hole cleaning is conducted through the guide pipe; an underwater concrete pouring step, wherein underwater concrete pouring is continuously carried out; and the guide pipe and the steel casing are pulled out, specifically, after underwater concrete pouring is completed, the guide pipe and the steel casing are pulled out slowly through a crane. The cast-in-place pile has the effect of solving the problem that the construction difficulty of the cast-in-place pile is large.
本申请涉及大直径超长灌注桩施工方法,涉及灌注桩施工技术的技术领域,其包括以下步骤:施工准备步骤:平整施工场地,并夯填密实;钢护筒埋设步骤:采用机械开挖埋设护筒;钻孔步骤:钻进过程中采用静态泥浆护壁;成孔检查步骤:当钻孔深度达到设计要求时,对孔位、孔径、孔深和倾斜度等进行检查;清孔步骤:采用换浆法进行清孔;钢筋笼制作安装步骤:桩基钢筋笼在钢筋场中集中制作;钢筋笼安装采用汽车吊;导管安装步骤:导管吊装入孔;二次清孔步骤:利用导管进行二次清孔;灌注水下混凝土步骤:水下混凝土灌注连续进行;拔除导管及钢护筒步骤:水下混凝土灌注完毕,通过吊车慢速拔出。本申请具有改善灌注桩施工时难度大的问题的效果。
Construction method of large-diameter super-long cast-in-place pile
大直径超长灌注桩施工方法
XIAO YING (Autor:in) / ZHANG YING (Autor:in) / WANG DESHENG (Autor:in) / XIE HUI (Autor:in)
31.03.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Large-diameter super-long cast-in-place pile construction method
Europäisches Patentamt | 2021
|Limited space large-diameter super-long cast-in-place pile construction method
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Europäisches Patentamt | 2021
|Europäisches Patentamt | 2021
|