Modular data center roof integrated construction method
The invention relates to the technical field, in particular to a modular data center roof integrated construction method which comprises the steps that steel structure modules and heat preservation plates are obtained, and a single module roof is constructed; the adjacent single module roofs are sealed and bonded, and a data center roof is constructed and formed; the data center roof is covered with an isolation layer so that the waterproof performance of the data center roof can be achieved; by means of the prefabricated steel structure modules and the heat preservation plates, construction in a concrete cast-in-place mode can be better avoided, on one hand, the construction efficiency can be better improved, and on the other hand, the construction efficiency can be improved while the steel structure modules and the heat preservation plates are assembled. Synchronous construction of roof waterproofing, building heat preservation and interior decoration is achieved through sealing and bonding treatment and isolation layer covering operation; the workload of a construction site can be relatively reduced, the construction period is shortened, and the labor cost is reduced.
本发明涉及技术领域,具体地说,涉及一种模块化数据中心屋面一体化构造方法,包括获取钢结构模块和保温板材,构建单个模块屋面;封粘处理相邻的所述单个模块屋面,构建形成数据中心屋面;于所述数据中心屋面处覆盖隔离层以实现所述数据中心屋面的防水性能;通过预制化钢结构模块和保温板材,能够较佳地避免采用混凝土现浇的形式施工,且一方面,能够较佳地提高施工效率,另一方面,能够在组装钢结构模块和保温板材的同时,通过封粘处理和覆盖隔离层的操作实现屋面防水、建筑保温以及内部装修的同步施工;能够相对减小施工现场的作业量,减少施工周期以及降低人工成本。
Modular data center roof integrated construction method
The invention relates to the technical field, in particular to a modular data center roof integrated construction method which comprises the steps that steel structure modules and heat preservation plates are obtained, and a single module roof is constructed; the adjacent single module roofs are sealed and bonded, and a data center roof is constructed and formed; the data center roof is covered with an isolation layer so that the waterproof performance of the data center roof can be achieved; by means of the prefabricated steel structure modules and the heat preservation plates, construction in a concrete cast-in-place mode can be better avoided, on one hand, the construction efficiency can be better improved, and on the other hand, the construction efficiency can be improved while the steel structure modules and the heat preservation plates are assembled. Synchronous construction of roof waterproofing, building heat preservation and interior decoration is achieved through sealing and bonding treatment and isolation layer covering operation; the workload of a construction site can be relatively reduced, the construction period is shortened, and the labor cost is reduced.
本发明涉及技术领域,具体地说,涉及一种模块化数据中心屋面一体化构造方法,包括获取钢结构模块和保温板材,构建单个模块屋面;封粘处理相邻的所述单个模块屋面,构建形成数据中心屋面;于所述数据中心屋面处覆盖隔离层以实现所述数据中心屋面的防水性能;通过预制化钢结构模块和保温板材,能够较佳地避免采用混凝土现浇的形式施工,且一方面,能够较佳地提高施工效率,另一方面,能够在组装钢结构模块和保温板材的同时,通过封粘处理和覆盖隔离层的操作实现屋面防水、建筑保温以及内部装修的同步施工;能够相对减小施工现场的作业量,减少施工周期以及降低人工成本。
Modular data center roof integrated construction method
一种模块化数据中心屋面一体化构造方法
SUN YUE (Autor:in) / YU YIFAN (Autor:in) / KANEKO OKU (Autor:in)
18.04.2023
Patent
Elektronische Ressource
Chinesisch
Modular roof mounted cooling system and method for data center
Europäisches Patentamt | 2021
|MODULAR ROOF MOUNTED COOLING SYSTEM AND METHOD FOR DATA CENTER
Europäisches Patentamt | 2020
|INTEGRATED ROOF MODULE AND MODULAR ROOF SYSTEM THEREOF
Europäisches Patentamt | 2023
|