Construction method for side wall of foundation pit of subway station
The invention relates to the field of metro station foundation pit construction, in particular to a metro station foundation pit side wall construction method which comprises the following steps that S1, a fender post working face is excavated; s2, arranging an opposite-pull screw rod, and enabling the axial direction of the opposite-pull screw rod to be perpendicular to the working face of the fender post; s3, steel bar meshes are laid, specifically, the steel bar meshes are bound on the opposite-pull screws, so that the steel bar meshes form a leveling plane; the split screws are painted and marked at equal intervals by taking the leveling surface as a reference to form marking surfaces; s4, the opposite-pull screws penetrate through the pouring sub-formworks, and the pouring sub-formworks are oppositely pulled and fixed with the painting marks as reference; a supporting assembly is installed on the side, away from the fender post, of the pouring sub-formwork, and the supporting assembly and the bottom of the foundation pit are fixed to support the pouring sub-formwork; s5, the concrete is poured horizontally in a layered mode; and S6, after the strength of the to-be-poured concrete reaches the formwork removal condition, formwork removal is conducted. The surface flatness of the side wall after pouring can be guaranteed.
本发明涉及地铁车站基坑的施工领域,具体涉及一种地铁车站基坑侧墙的施工方法,包括如下步骤:S1、围护桩作业面开挖;S2、布置对拉螺杆,使对拉螺杆的轴向方向垂直于围护桩作业面;S3、敷设钢筋网片,在对拉螺杆上绑扎钢筋网片,使钢筋网片形成找平面;以找平面为基准在各对拉螺杆上等距离刷漆标记形成标记面;S4、使对拉螺杆穿过浇筑子模板,并以刷漆标记为参考对拉固定各浇筑子模板;在浇筑子模板远离围护桩的一侧安装支护组件,并将支护组件与基坑底部固定对浇筑子模板进行支撑;S5、混凝土按水平分层浇筑;S6、待浇筑的混凝土强度达到拆模条件后进行拆模。本发明能够保证侧墙浇筑后的表面平整度。
Construction method for side wall of foundation pit of subway station
The invention relates to the field of metro station foundation pit construction, in particular to a metro station foundation pit side wall construction method which comprises the following steps that S1, a fender post working face is excavated; s2, arranging an opposite-pull screw rod, and enabling the axial direction of the opposite-pull screw rod to be perpendicular to the working face of the fender post; s3, steel bar meshes are laid, specifically, the steel bar meshes are bound on the opposite-pull screws, so that the steel bar meshes form a leveling plane; the split screws are painted and marked at equal intervals by taking the leveling surface as a reference to form marking surfaces; s4, the opposite-pull screws penetrate through the pouring sub-formworks, and the pouring sub-formworks are oppositely pulled and fixed with the painting marks as reference; a supporting assembly is installed on the side, away from the fender post, of the pouring sub-formwork, and the supporting assembly and the bottom of the foundation pit are fixed to support the pouring sub-formwork; s5, the concrete is poured horizontally in a layered mode; and S6, after the strength of the to-be-poured concrete reaches the formwork removal condition, formwork removal is conducted. The surface flatness of the side wall after pouring can be guaranteed.
本发明涉及地铁车站基坑的施工领域,具体涉及一种地铁车站基坑侧墙的施工方法,包括如下步骤:S1、围护桩作业面开挖;S2、布置对拉螺杆,使对拉螺杆的轴向方向垂直于围护桩作业面;S3、敷设钢筋网片,在对拉螺杆上绑扎钢筋网片,使钢筋网片形成找平面;以找平面为基准在各对拉螺杆上等距离刷漆标记形成标记面;S4、使对拉螺杆穿过浇筑子模板,并以刷漆标记为参考对拉固定各浇筑子模板;在浇筑子模板远离围护桩的一侧安装支护组件,并将支护组件与基坑底部固定对浇筑子模板进行支撑;S5、混凝土按水平分层浇筑;S6、待浇筑的混凝土强度达到拆模条件后进行拆模。本发明能够保证侧墙浇筑后的表面平整度。
Construction method for side wall of foundation pit of subway station
一种地铁车站基坑侧墙的施工方法
LING TAO (Autor:in) / XIAO LEI (Autor:in) / TAN CHAO (Autor:in) / LIU HUAPING (Autor:in) / LIU YUNLONG (Autor:in) / WEI LEYI (Autor:in) / TANG YU (Autor:in) / PENG XUEJUN (Autor:in) / ZHANG SHENG (Autor:in) / HUANG JIANQIU (Autor:in)
25.04.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Fabricated subway station side wall and diaphragm wall connection construction method
Europäisches Patentamt | 2023
|Subway station side wall quick-release formwork system and construction method
Europäisches Patentamt | 2024
|Subway station side wall large formwork waterproof system and construction method
Europäisches Patentamt | 2024
|Subway station deep foundation pit excavation construction method
Europäisches Patentamt | 2015
|Subway station foundation pit construction command platform
Europäisches Patentamt | 2023
|