The invention provides a construction method of a dock. The construction method comprises the steps that a steel pipe cylinder structure is assembled, specifically, the steel pipe cylinder structure is assembled and provided with a plurality of first steel pipes and I-shaped steel for connecting every two adjacent first steel pipes; construction of the steel pipe cylinder structures: driving the steel pipe cylinder structures to construction positions; steel sheet piles are constructed, specifically, the steel sheet piles are driven between the adjacent steel pipe cylinder structures; construction of dock gate structures: connecting the head and tail steel tube cylinder structures with the two dock gate piers respectively to form a closed dock; dock wall connection: water in the dock is discharged, and a post-cast strip is cast between the two opposite first baffles; backfilling between the first baffle and the steel sheet pile to form a second backfilling part; and surface layer construction: constructing above the steel pipe cylinder structure to form a surface layer.
本申请提供了一种船坞的施工方法,包括:钢管圆筒结构的组装:组装所述钢管圆筒结构具有多个第一钢管以及连接两个相邻的第一钢管的工字钢;钢管圆筒结构的施工:将各钢管圆筒结构打设到施工位置;钢板桩施工:在相邻的钢管圆筒结构之间打设钢板桩;坞门结构的施工:首尾两个钢管圆筒结构分别与两个坞门墩相连,以形成封闭的船坞;坞壁连接:排出船坞内的水,在相对的两个第一挡板之间浇筑后浇带;在第一挡板和钢板桩之间回填,形成第二回填部;以及面层施工:在钢管圆筒结构上方施工形成面层。
Construction method of dock
The invention provides a construction method of a dock. The construction method comprises the steps that a steel pipe cylinder structure is assembled, specifically, the steel pipe cylinder structure is assembled and provided with a plurality of first steel pipes and I-shaped steel for connecting every two adjacent first steel pipes; construction of the steel pipe cylinder structures: driving the steel pipe cylinder structures to construction positions; steel sheet piles are constructed, specifically, the steel sheet piles are driven between the adjacent steel pipe cylinder structures; construction of dock gate structures: connecting the head and tail steel tube cylinder structures with the two dock gate piers respectively to form a closed dock; dock wall connection: water in the dock is discharged, and a post-cast strip is cast between the two opposite first baffles; backfilling between the first baffle and the steel sheet pile to form a second backfilling part; and surface layer construction: constructing above the steel pipe cylinder structure to form a surface layer.
本申请提供了一种船坞的施工方法,包括:钢管圆筒结构的组装:组装所述钢管圆筒结构具有多个第一钢管以及连接两个相邻的第一钢管的工字钢;钢管圆筒结构的施工:将各钢管圆筒结构打设到施工位置;钢板桩施工:在相邻的钢管圆筒结构之间打设钢板桩;坞门结构的施工:首尾两个钢管圆筒结构分别与两个坞门墩相连,以形成封闭的船坞;坞壁连接:排出船坞内的水,在相对的两个第一挡板之间浇筑后浇带;在第一挡板和钢板桩之间回填,形成第二回填部;以及面层施工:在钢管圆筒结构上方施工形成面层。
Construction method of dock
船坞的施工方法
LI YIYONG (Autor:in) / LI MAOYUAN (Autor:in) / CHEN XIAO (Autor:in) / DU CHUANG (Autor:in) / NIU LEI (Autor:in) / FENG YUXI (Autor:in) / ZHANG JIANNING (Autor:in)
23.05.2023
Patent
Elektronische Ressource
Chinesisch
Engineering Index Backfile | 1943
|Engineering Index Backfile | 1929
Engineering Index Backfile | 1902
|Subaqueous dry dock construction
Engineering Index Backfile | 1944
|