Combined device and method for water anchor pile method vertical static load test
The invention relates to a combined device and method for a vertical static load test of an overwater anchor pile method. The two portal frames are arranged at the two ends of the overwater bearing platform respectively, the steel beam penetrates through the space of the #-shaped foundation pile connecting assembly I to be tested and the space of the #-shaped anchor pile connecting assembly II, and the two ends of the steel beam are arranged below cross beams of the portal frames in a suspended mode respectively. The to-be-tested foundation pile connecting assembly I is arranged in the middle of the steel beam, the two anchor pile connecting disc assemblies II are arranged at the two ends of the steel beam respectively, and the lower end face of a connecting disc I of the to-be-tested foundation pile connecting assembly I and the lower end face of a connecting disc II of the anchor pile connecting assembly II are located on the same horizontal plane. The anti-pulling jack is arranged between an upper tensile small cross beam I of the to-be-tested foundation pile connecting assembly I and the steel beam; the compression-resistant jack is arranged between the steel beam and the connecting disc I of the to-be-tested foundation pile connecting assembly I; and the recording platform is arranged beside the to-be-tested foundation pile below the middle part of the steel beam. According to the invention, compression resistance and pulling resistance static load test devices are combined into one, the conversion can be easily realized, the installation is fast, and the test result is reliable.
本发明涉及一种用于水上锚桩法竖向静载试验的联合装置及方法。两个龙门架分别设置在水上承载平台的两端,钢梁穿过“井”字形的待测基桩连接组件Ⅰ和锚桩连接组件Ⅱ的空间,两端分别悬吊设置在龙门架横梁的下方;待测基桩连接组件Ⅰ设置在钢梁的中间,两个锚桩连接盘组件Ⅱ分别设置在钢梁的两端,待测基桩连接组件Ⅰ的连接盘Ⅰ的下端面和锚桩连接组件Ⅱ的连接盘Ⅱ的下端面位于同一水平面;抗拔千斤顶设置在待测基桩连接组件Ⅰ的上抗拉小横梁Ⅰ和钢梁之间;抗压千斤顶设置在钢梁和待测基桩连接组件Ⅰ的连接盘Ⅰ之间;记录平台设置在钢梁中部下方的待测基桩旁。本发明将抗压、抗拔静载试验装置合二为一,可轻松转换、安装快速、试验结果可靠。
Combined device and method for water anchor pile method vertical static load test
The invention relates to a combined device and method for a vertical static load test of an overwater anchor pile method. The two portal frames are arranged at the two ends of the overwater bearing platform respectively, the steel beam penetrates through the space of the #-shaped foundation pile connecting assembly I to be tested and the space of the #-shaped anchor pile connecting assembly II, and the two ends of the steel beam are arranged below cross beams of the portal frames in a suspended mode respectively. The to-be-tested foundation pile connecting assembly I is arranged in the middle of the steel beam, the two anchor pile connecting disc assemblies II are arranged at the two ends of the steel beam respectively, and the lower end face of a connecting disc I of the to-be-tested foundation pile connecting assembly I and the lower end face of a connecting disc II of the anchor pile connecting assembly II are located on the same horizontal plane. The anti-pulling jack is arranged between an upper tensile small cross beam I of the to-be-tested foundation pile connecting assembly I and the steel beam; the compression-resistant jack is arranged between the steel beam and the connecting disc I of the to-be-tested foundation pile connecting assembly I; and the recording platform is arranged beside the to-be-tested foundation pile below the middle part of the steel beam. According to the invention, compression resistance and pulling resistance static load test devices are combined into one, the conversion can be easily realized, the installation is fast, and the test result is reliable.
本发明涉及一种用于水上锚桩法竖向静载试验的联合装置及方法。两个龙门架分别设置在水上承载平台的两端,钢梁穿过“井”字形的待测基桩连接组件Ⅰ和锚桩连接组件Ⅱ的空间,两端分别悬吊设置在龙门架横梁的下方;待测基桩连接组件Ⅰ设置在钢梁的中间,两个锚桩连接盘组件Ⅱ分别设置在钢梁的两端,待测基桩连接组件Ⅰ的连接盘Ⅰ的下端面和锚桩连接组件Ⅱ的连接盘Ⅱ的下端面位于同一水平面;抗拔千斤顶设置在待测基桩连接组件Ⅰ的上抗拉小横梁Ⅰ和钢梁之间;抗压千斤顶设置在钢梁和待测基桩连接组件Ⅰ的连接盘Ⅰ之间;记录平台设置在钢梁中部下方的待测基桩旁。本发明将抗压、抗拔静载试验装置合二为一,可轻松转换、安装快速、试验结果可靠。
Combined device and method for water anchor pile method vertical static load test
一种用于水上锚桩法竖向静载试验的联合装置及方法
HAI BAOQUAN (Autor:in) / HUANG JIANJUN (Autor:in) / ZHANG YING (Autor:in) / DONG WEIQIANG (Autor:in) / WANG CHONG (Autor:in) / YANG JUN (Autor:in) / LI DONG (Autor:in) / LI WANSHAN (Autor:in) / WANG HAO (Autor:in) / ZHAO ZHIRONG (Autor:in)
26.05.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile foundation static load test method adopting construction pile as anchor
Europäisches Patentamt | 2022
|Adjustable anchor pile method static load testing device
Europäisches Patentamt | 2023
|Foundation pile vertical compressive static load test method
Europäisches Patentamt | 2021
|Foundation pile static load test method adopting anchor cable to apply prestress
Europäisches Patentamt | 2024
|