Drilling pile operation platform construction technology for bridge construction
The invention relates to the technical field of bridge construction, and discloses a construction process of a drilling pile operation platform for bridge construction, which comprises the following steps of: 1, excavating a supporting foundation pit at a position where an operation platform needs to be arranged; secondly, a supporting mechanism is built on the foundation pit, the foundation pit is fixed through the supporting mechanism, and the foundation pit is stabilized; thirdly, an existing jacking device is assembled and installed on a supporting mechanism of the foundation pit, and the lifting effect is achieved; fourthly, an existing operation platform (modularization) is placed on the jacking device and lifted through the jacking device, through a function modularization mode, other functions of the operation platform except basic functions are all additional functions, functional assemblies can be flexibly increased or decreased through the modularization mode, and the operation platform is convenient to use. Redundancy of functions of the action platform is avoided, and meanwhile complete functions of the action platform can be guaranteed in an increasing mode.
本发明涉及桥梁建设技术领域,且公开了一种桥梁建设用钻孔桩作业平台施工工艺,包括以下步骤:步骤一、在需要设置作业平台的位置进行支撑基坑开挖;步骤二、在基坑上搭建支撑机构,通过支撑机构固定基坑,并使基坑稳定;步骤三、将现有的顶升装置组装,并安装到基坑的支撑机构上,作升降作用;步骤四、将现有的作业平台(模块化)放置到顶升装置上,并由顶升装置进行升降,通过功能模块化的方式,可以使作业平台除了基础功能之外,其他的功能均是附加功能,利用模块化的方式可以灵活的增加或者减少功能组件,避免作用平台功能的冗余,同时还能通过增加的方式保证作用平台的功能齐全。
Drilling pile operation platform construction technology for bridge construction
The invention relates to the technical field of bridge construction, and discloses a construction process of a drilling pile operation platform for bridge construction, which comprises the following steps of: 1, excavating a supporting foundation pit at a position where an operation platform needs to be arranged; secondly, a supporting mechanism is built on the foundation pit, the foundation pit is fixed through the supporting mechanism, and the foundation pit is stabilized; thirdly, an existing jacking device is assembled and installed on a supporting mechanism of the foundation pit, and the lifting effect is achieved; fourthly, an existing operation platform (modularization) is placed on the jacking device and lifted through the jacking device, through a function modularization mode, other functions of the operation platform except basic functions are all additional functions, functional assemblies can be flexibly increased or decreased through the modularization mode, and the operation platform is convenient to use. Redundancy of functions of the action platform is avoided, and meanwhile complete functions of the action platform can be guaranteed in an increasing mode.
本发明涉及桥梁建设技术领域,且公开了一种桥梁建设用钻孔桩作业平台施工工艺,包括以下步骤:步骤一、在需要设置作业平台的位置进行支撑基坑开挖;步骤二、在基坑上搭建支撑机构,通过支撑机构固定基坑,并使基坑稳定;步骤三、将现有的顶升装置组装,并安装到基坑的支撑机构上,作升降作用;步骤四、将现有的作业平台(模块化)放置到顶升装置上,并由顶升装置进行升降,通过功能模块化的方式,可以使作业平台除了基础功能之外,其他的功能均是附加功能,利用模块化的方式可以灵活的增加或者减少功能组件,避免作用平台功能的冗余,同时还能通过增加的方式保证作用平台的功能齐全。
Drilling pile operation platform construction technology for bridge construction
一种桥梁建设用钻孔桩作业平台施工工艺
HAO XIAOJUN (Autor:in) / WANG ZENGQIANG (Autor:in) / SUN LIWEI (Autor:in) / ZHANG HONGLING (Autor:in) / CHEN ZHAOYONG (Autor:in) / LI DEHUA (Autor:in) / LIU SIHUI (Autor:in) / FANG JIANJIAN (Autor:in) / ZHOU YONG (Autor:in) / YUAN LIANWANG (Autor:in)
02.06.2023
Patent
Elektronische Ressource
Chinesisch
Separable railway bridge pile foundation drilling platform and construction method thereof
Europäisches Patentamt | 2024
|Slope bridge construction pile foundation bearing platform
Europäisches Patentamt | 2024
|Fabricated pile foundation drilling platform and construction method
Europäisches Patentamt | 2024
|