Method for observing and evaluating real settlement during construction period of earth-rock filling project
According to the real settlement observation and evaluation method for the earth-rock filling project during the construction period, the filling layer thickness and settlement amount detection device is used for accurately obtaining the initial compaction layer thickness of each filling layer as the core, and based on observation data such as the top surface elevation of a filling body before and after filling construction of each layer, the real settlement of the filling body is evaluated. According to the method, the total settlement amount of the filling body can be completely and truly observed, the theoretical total settlement amount and the settlement completion rate of the filling body can be calculated, the method is used for predicting the follow-up settlement amount possibly generated in the future, and important basic data are provided for construction arrangement, verification design and the like.
本发明提供了一种土石填筑工程施工期真实沉降观测与评价方法,填筑层厚度与沉降量检测装置,以准确获得每个填筑层的初始压实层厚为核心,基于每层填筑施工前后,填筑体的顶面高程等观测数据,进行完整、真实的填筑体总沉降量观测,还可以计算填筑体的理论总沉降量与“沉降完成率”,用于预测未来可能产生的后续沉降量,对施工安排和验证设计等提供重要的基础数据。
Method for observing and evaluating real settlement during construction period of earth-rock filling project
According to the real settlement observation and evaluation method for the earth-rock filling project during the construction period, the filling layer thickness and settlement amount detection device is used for accurately obtaining the initial compaction layer thickness of each filling layer as the core, and based on observation data such as the top surface elevation of a filling body before and after filling construction of each layer, the real settlement of the filling body is evaluated. According to the method, the total settlement amount of the filling body can be completely and truly observed, the theoretical total settlement amount and the settlement completion rate of the filling body can be calculated, the method is used for predicting the follow-up settlement amount possibly generated in the future, and important basic data are provided for construction arrangement, verification design and the like.
本发明提供了一种土石填筑工程施工期真实沉降观测与评价方法,填筑层厚度与沉降量检测装置,以准确获得每个填筑层的初始压实层厚为核心,基于每层填筑施工前后,填筑体的顶面高程等观测数据,进行完整、真实的填筑体总沉降量观测,还可以计算填筑体的理论总沉降量与“沉降完成率”,用于预测未来可能产生的后续沉降量,对施工安排和验证设计等提供重要的基础数据。
Method for observing and evaluating real settlement during construction period of earth-rock filling project
一种土石填筑工程施工期真实沉降观测与评价方法
GUO GUANGWEN (Autor:in) / TAN KAIYAN (Autor:in) / ZHANG XINYUAN (Autor:in) / HU DIZHONG (Autor:in) / ZHANG ZHIKUI (Autor:in) / LI ZHANBEI (Autor:in) / HUANG XIAOHONG (Autor:in) / ZHANG CHENGKUO (Autor:in) / SUN WENSHENG (Autor:in) / PENG JIAFENG (Autor:in)
09.06.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
/
E02D
FOUNDATIONS
,
Gründungen
/
G01C
Messen von Entfernungen, Höhen, Neigungen oder Richtungen
,
MEASURING DISTANCES, LEVELS OR BEARINGS
British Library Conference Proceedings | 2011
|Standardized construction vehicle and construction method for earth-rock mixed filling
Europäisches Patentamt | 2022
|Method and device for observing layered settlement of high fill earth
Europäisches Patentamt | 2015
|Mountainous area earth-rock mixed filling high embankment filling construction device and method
Europäisches Patentamt | 2024
|