Pre-righting hole-forming construction method for extremely-hard inclined rock large-diameter pile
The invention discloses a pre-righting hole-forming construction method for a super-hard inclined rock large-diameter pile. The pre-righting hole-forming construction method comprises the following steps that (1) a center pillar is specially surveyed; (2) a wall protection pile hole is drilled in the outer edge of the center pillar drill hole on the opposite side of the bedrock to the depth of the bedrock in a jumping mode; then a thick-wall steel pipe is put down in the wall protection pile hole; (3) retaining pile occlusion holes are drilled in the jumping intervals, and the thick-wall steel pipes are lowered after drilling is completed; (4) connecting rings are hung between the hooks of the adjacent thick-wall steel pipes; (5) filling a soilbag into a gap between the thick-wall steel pipe and the retaining wall pile hole, filling silty-fine sand, and vibrating and compacting; (6) drilling the center pillar and following the pile casing; (7) middle stand column construction; and (8) recycling the auxiliary equipment on the outer side of the drilling hole of the middle stand column. The method has the advantages that 1, the thick-wall steel pipe is used as a supporting material, so that the construction is fast, and the perpendicularity is ensured; the sand pumping technology is adopted to dismantle auxiliary devices, and dismantling is convenient and fast; and 3, the safety risk caused by mutual locking and hooking of underground components is effectively avoided.
本发明公开一种极硬斜岩大直径桩预扶正成孔施工方法,步骤如下:(1).中立柱专勘;(2).在基岩对侧中立柱钻孔的外边缘跳打护壁桩孔至基岩深度;然后在护壁桩孔内下放厚壁钢管;(3).在跳打间隔处钻进护壁桩咬合孔,钻孔完成后也下放厚壁钢管;(4).相邻的厚壁钢管的挂钩间挂上连接环;(5).在厚壁钢管与护壁桩孔的间隙处塞进土工袋、填筑粉细砂并振动密实;(6).中立柱钻孔并跟进护筒;(7).中立柱施工;(8).中立柱钻孔外侧辅助设备的回收。本发明的优点是:1.采用了厚壁钢管作为支撑材料,施工快捷,垂直度得到保证;2.采用抽砂技术拆除辅助设置,拆除便捷;3.有效避免了地下构件相互锁紧、钩连诱发的安全风险。
Pre-righting hole-forming construction method for extremely-hard inclined rock large-diameter pile
The invention discloses a pre-righting hole-forming construction method for a super-hard inclined rock large-diameter pile. The pre-righting hole-forming construction method comprises the following steps that (1) a center pillar is specially surveyed; (2) a wall protection pile hole is drilled in the outer edge of the center pillar drill hole on the opposite side of the bedrock to the depth of the bedrock in a jumping mode; then a thick-wall steel pipe is put down in the wall protection pile hole; (3) retaining pile occlusion holes are drilled in the jumping intervals, and the thick-wall steel pipes are lowered after drilling is completed; (4) connecting rings are hung between the hooks of the adjacent thick-wall steel pipes; (5) filling a soilbag into a gap between the thick-wall steel pipe and the retaining wall pile hole, filling silty-fine sand, and vibrating and compacting; (6) drilling the center pillar and following the pile casing; (7) middle stand column construction; and (8) recycling the auxiliary equipment on the outer side of the drilling hole of the middle stand column. The method has the advantages that 1, the thick-wall steel pipe is used as a supporting material, so that the construction is fast, and the perpendicularity is ensured; the sand pumping technology is adopted to dismantle auxiliary devices, and dismantling is convenient and fast; and 3, the safety risk caused by mutual locking and hooking of underground components is effectively avoided.
本发明公开一种极硬斜岩大直径桩预扶正成孔施工方法,步骤如下:(1).中立柱专勘;(2).在基岩对侧中立柱钻孔的外边缘跳打护壁桩孔至基岩深度;然后在护壁桩孔内下放厚壁钢管;(3).在跳打间隔处钻进护壁桩咬合孔,钻孔完成后也下放厚壁钢管;(4).相邻的厚壁钢管的挂钩间挂上连接环;(5).在厚壁钢管与护壁桩孔的间隙处塞进土工袋、填筑粉细砂并振动密实;(6).中立柱钻孔并跟进护筒;(7).中立柱施工;(8).中立柱钻孔外侧辅助设备的回收。本发明的优点是:1.采用了厚壁钢管作为支撑材料,施工快捷,垂直度得到保证;2.采用抽砂技术拆除辅助设置,拆除便捷;3.有效避免了地下构件相互锁紧、钩连诱发的安全风险。
Pre-righting hole-forming construction method for extremely-hard inclined rock large-diameter pile
一种极硬斜岩大直径桩预扶正成孔施工方法
YANG JIANJUN (Autor:in) / DAI WUKUI (Autor:in) / ZHAO ZHONGLIANG (Autor:in) / ZHANG JIAN (Autor:in) / CHE JINZE (Autor:in) / LIU ZIWEI (Autor:in) / GUO RAN (Autor:in) / ZHANG HONGYANG (Autor:in) / XING YUESHAN (Autor:in) / LIN HONGXU (Autor:in)
23.06.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Hole-forming construction process for hard rock large-diameter hole pile
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Hole-forming construction method for large-diameter pile foundation
Europäisches Patentamt | 2024
|Hard rock stratum square pile hole forming pouring construction method
Europäisches Patentamt | 2021
|Pore-forming method of hard rock foundation pile with large diameter
Europäisches Patentamt | 2015
|