Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Open caisson type cooling tower construction method and open caisson type cooling tower structure
The invention relates to the technical field of subway engineering, and discloses an open caisson type cooling tower construction method which comprises the following steps: S1, manufacturing an open caisson; s2, after the sinking degree of the open caisson is determined, a jet grouting pile is constructed; s3, a concrete cushion layer is laid, a cooling tower bottom plate and a pipe gallery channel bottom plate are constructed, and a pipe gallery channel top plate is constructed; s4, a soil body at the joint of the open caisson and the ventilation pavilion side wall is excavated; s5, a steel sealing door and bricks on the well wall are dismantled, and a connector bottom plate, a connector side wall and a connector top plate are constructed at the connector; and S6, backfilling and covering soil, constructing a cooling tower foundation and stair columns, constructing stair plates, installing a cooling tower, and erecting a cooling tower ceiling. The invention further discloses an open caisson type cooling tower structure. The well wall of the open caisson is also used as the side wall of the main body structure of the cooling tower, so that an enclosure structure can be saved, the construction efficiency of the cooling tower structure is improved, and the influence on the surrounding environment and the construction cost are reduced.
本发明本发明涉及地铁工程技术领域,公开了一种沉井式冷却塔施工方法,包括以下步骤:S1、制造沉井;S2、沉井下沉度后,施工旋喷桩;S3、铺设混凝土垫层,施工冷却塔底板和管廊通道底板,施工管廊通道顶板;S4、开挖沉井与风亭侧墙接口处土体;S5、拆除井壁上的钢封门和砌砖,在接口处施工接口底板、接口侧墙和接口顶板;S6、回填覆土,施工冷却塔基础和楼梯柱,施工楼梯板,安装冷却塔,架设冷却塔顶棚,还公开了一种沉井式冷却塔结构;本发明的沉井井壁兼做冷却塔主体结构侧墙,可节省围护结构,提高冷却塔结构施工效率,降低对周边环境的影响和工程造价。
Open caisson type cooling tower construction method and open caisson type cooling tower structure
The invention relates to the technical field of subway engineering, and discloses an open caisson type cooling tower construction method which comprises the following steps: S1, manufacturing an open caisson; s2, after the sinking degree of the open caisson is determined, a jet grouting pile is constructed; s3, a concrete cushion layer is laid, a cooling tower bottom plate and a pipe gallery channel bottom plate are constructed, and a pipe gallery channel top plate is constructed; s4, a soil body at the joint of the open caisson and the ventilation pavilion side wall is excavated; s5, a steel sealing door and bricks on the well wall are dismantled, and a connector bottom plate, a connector side wall and a connector top plate are constructed at the connector; and S6, backfilling and covering soil, constructing a cooling tower foundation and stair columns, constructing stair plates, installing a cooling tower, and erecting a cooling tower ceiling. The invention further discloses an open caisson type cooling tower structure. The well wall of the open caisson is also used as the side wall of the main body structure of the cooling tower, so that an enclosure structure can be saved, the construction efficiency of the cooling tower structure is improved, and the influence on the surrounding environment and the construction cost are reduced.
本发明本发明涉及地铁工程技术领域,公开了一种沉井式冷却塔施工方法,包括以下步骤:S1、制造沉井;S2、沉井下沉度后,施工旋喷桩;S3、铺设混凝土垫层,施工冷却塔底板和管廊通道底板,施工管廊通道顶板;S4、开挖沉井与风亭侧墙接口处土体;S5、拆除井壁上的钢封门和砌砖,在接口处施工接口底板、接口侧墙和接口顶板;S6、回填覆土,施工冷却塔基础和楼梯柱,施工楼梯板,安装冷却塔,架设冷却塔顶棚,还公开了一种沉井式冷却塔结构;本发明的沉井井壁兼做冷却塔主体结构侧墙,可节省围护结构,提高冷却塔结构施工效率,降低对周边环境的影响和工程造价。
Open caisson type cooling tower construction method and open caisson type cooling tower structure
一种沉井式冷却塔施工方法及沉井式冷却塔结构
LI FANGBAO (Autor:in) / CHEN XIANGYU (Autor:in) / ZHOU CANLANG (Autor:in) / WEI XIANKUN (Autor:in) / CHEN YUAN (Autor:in) / LI ZHI (Autor:in) / PAN QIAN (Autor:in) / LIU JIAFU (Autor:in) / XIE YUANFA (Autor:in) / ZHANG YONG (Autor:in)
23.06.2023
Patent
Elektronische Ressource
Chinesisch
Open caisson construction method and open caisson structure
Europäisches Patentamt | 2020
|Open caisson construction method and open caisson structure
Europäisches Patentamt | 2023
|Open caisson structure and open caisson construction method
Europäisches Patentamt | 2020
|Open caisson guiding structure and open caisson construction method
Europäisches Patentamt | 2024
|Open caisson tower footing inclination monitoring equipment
Europäisches Patentamt | 2020
|