Foundation pit excavation and steel pipe support construction method
The invention relates to the technical field of foundation pit excavation, and discloses a foundation pit excavation and steel pipe support construction method which comprises the following steps: S1, measuring the position of an excavated foundation pit and the attributes of surrounding soil; s2, the foundation pit size is designed according to the soil data; s3, determining an excavation scheme according to the soil data and the design size of the foundation pit; s4, a supporting scheme is determined according to the excavation scheme, the soil data and the foundation pit size; s5, the foundation pit is excavated according to the excavation scheme; s6, steel pipe supports are arranged according to the supporting scheme; and S7, foundation pit opening is completed, foundation pit fixing is conducted through steel pipe supporting, the size of the foundation pit is automatically recognized through camera shooting in cooperation with an intelligent algorithm, the excavation depth of the foundation pit is monitored in real time, construction site monitoring equipment is automatically on duty, manual foundation pit depth measurement is reduced, and therefore personnel investment is reduced, and the construction efficiency is improved. And cross operation of operators and excavation machinery is avoided, personal safety is guaranteed, and safety accidents are reduced.
本发明涉及基坑开挖技术领域,且公开了一种基坑开挖与钢管支护施工方法,包括以下步骤:S1、对开挖基坑位置以及周围的土壤属性进行测量;S2、根据土壤数据设计基坑尺寸;S3、根据土壤数据以及基坑设计尺寸确定开挖方案;S4、根据开挖方案、土壤数据以及基坑尺寸确定支撑方案;S5、根据开挖方案开挖基坑;S6、根据支撑方案设置钢管支护;S7、完成基坑开完,并通过钢管支护进行基坑固定,通过摄像配合智能算法自动识别出基坑的尺寸,实时监测基坑开挖深度,施工现场监控设备自动值守,减少了人工进行基坑深度的测量,从而减少人员投入,避免了作业人员与开挖机械的交叉作业,保证了人身安全,减少了安全事故的发生。
Foundation pit excavation and steel pipe support construction method
The invention relates to the technical field of foundation pit excavation, and discloses a foundation pit excavation and steel pipe support construction method which comprises the following steps: S1, measuring the position of an excavated foundation pit and the attributes of surrounding soil; s2, the foundation pit size is designed according to the soil data; s3, determining an excavation scheme according to the soil data and the design size of the foundation pit; s4, a supporting scheme is determined according to the excavation scheme, the soil data and the foundation pit size; s5, the foundation pit is excavated according to the excavation scheme; s6, steel pipe supports are arranged according to the supporting scheme; and S7, foundation pit opening is completed, foundation pit fixing is conducted through steel pipe supporting, the size of the foundation pit is automatically recognized through camera shooting in cooperation with an intelligent algorithm, the excavation depth of the foundation pit is monitored in real time, construction site monitoring equipment is automatically on duty, manual foundation pit depth measurement is reduced, and therefore personnel investment is reduced, and the construction efficiency is improved. And cross operation of operators and excavation machinery is avoided, personal safety is guaranteed, and safety accidents are reduced.
本发明涉及基坑开挖技术领域,且公开了一种基坑开挖与钢管支护施工方法,包括以下步骤:S1、对开挖基坑位置以及周围的土壤属性进行测量;S2、根据土壤数据设计基坑尺寸;S3、根据土壤数据以及基坑设计尺寸确定开挖方案;S4、根据开挖方案、土壤数据以及基坑尺寸确定支撑方案;S5、根据开挖方案开挖基坑;S6、根据支撑方案设置钢管支护;S7、完成基坑开完,并通过钢管支护进行基坑固定,通过摄像配合智能算法自动识别出基坑的尺寸,实时监测基坑开挖深度,施工现场监控设备自动值守,减少了人工进行基坑深度的测量,从而减少人员投入,避免了作业人员与开挖机械的交叉作业,保证了人身安全,减少了安全事故的发生。
Foundation pit excavation and steel pipe support construction method
一种基坑开挖与钢管支护施工方法
WU KEHUA (Autor:in) / KONG CHENGUANG (Autor:in) / DONG BO (Autor:in) / LI ZHEN (Autor:in) / WANG YANPEI (Autor:in) / LI QING (Autor:in) / GAO WENCHENG (Autor:in) / YUAN LIANWANG (Autor:in)
27.06.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
/
G01B
MEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS
,
Messen der Länge, der Dicke oder ähnlicher linearer Abmessungen
/
G01N
Untersuchen oder Analysieren von Stoffen durch Bestimmen ihrer chemischen oder physikalischen Eigenschaften
,
INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
/
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
Europäisches Patentamt | 2022
|Deep foundation pit excavation and support construction method
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Deep foundation pit secondary excavation and support construction method
Europäisches Patentamt | 2021
|STEEL PIPE FOR INNER EXCAVATION PILE CONSTRUCTION METHOD
Europäisches Patentamt | 2020
|