Prefabricated anti-seepage anchoring structure of steep rock slope and construction method
The invention discloses a prefabricated anti-seepage anchoring structure of a steep rock slope and a construction method. The prefabricated anti-seepage anchoring structure comprises an anchoring part and a prefabricated part. The multiple anchoring parts are fixed to the preset positions of the slope, the prefabricated part is fixed to at least one anchoring part, and an anchoring groove is formed in the fixed prefabricated part; a sprayed concrete layer is formed on the side slope, a reinforcing mesh is arranged in the sprayed concrete layer, and a plurality of anchoring parts are connected with the reinforcing mesh; an anti-seepage system is laid on the sprayed concrete layer and the prefabricated parts, the anti-seepage system is anchored through anchoring concrete filled in an anchoring groove, and the upper space of the anchoring groove is also used as a drainage ditch. The prefabricated part is fixed to the side slope through the anchoring part, and the anti-seepage system is anchored to the prefabricated part; the slope soil body can be reinforced, and anchoring of an anti-seepage system on a steep slope can be achieved.
本发明公开了一种陡峭岩质边坡的预制防渗锚固结构及施工方法,包括:锚固件和预制构件;多个锚固件固定在边坡的预设位置,预制构件固定在至少一个锚固件上,且固定后的预制构件上形成有锚固沟;边坡上形成有喷射混凝土层,喷射混凝土层内设有钢筋网,多个锚固件与钢筋网相连接;喷射混凝土层和预制构件上铺设有防渗系统,防渗系统通过填充于锚固沟的锚固混凝土进行锚固,锚固沟上部空间兼做排水沟。本发明通过锚固件将预制构件固定在边坡上,并将防渗系统锚固在预制构件上;其既能加固边坡土体,又能实现防渗系统在陡峭边坡的锚固。
Prefabricated anti-seepage anchoring structure of steep rock slope and construction method
The invention discloses a prefabricated anti-seepage anchoring structure of a steep rock slope and a construction method. The prefabricated anti-seepage anchoring structure comprises an anchoring part and a prefabricated part. The multiple anchoring parts are fixed to the preset positions of the slope, the prefabricated part is fixed to at least one anchoring part, and an anchoring groove is formed in the fixed prefabricated part; a sprayed concrete layer is formed on the side slope, a reinforcing mesh is arranged in the sprayed concrete layer, and a plurality of anchoring parts are connected with the reinforcing mesh; an anti-seepage system is laid on the sprayed concrete layer and the prefabricated parts, the anti-seepage system is anchored through anchoring concrete filled in an anchoring groove, and the upper space of the anchoring groove is also used as a drainage ditch. The prefabricated part is fixed to the side slope through the anchoring part, and the anti-seepage system is anchored to the prefabricated part; the slope soil body can be reinforced, and anchoring of an anti-seepage system on a steep slope can be achieved.
本发明公开了一种陡峭岩质边坡的预制防渗锚固结构及施工方法,包括:锚固件和预制构件;多个锚固件固定在边坡的预设位置,预制构件固定在至少一个锚固件上,且固定后的预制构件上形成有锚固沟;边坡上形成有喷射混凝土层,喷射混凝土层内设有钢筋网,多个锚固件与钢筋网相连接;喷射混凝土层和预制构件上铺设有防渗系统,防渗系统通过填充于锚固沟的锚固混凝土进行锚固,锚固沟上部空间兼做排水沟。本发明通过锚固件将预制构件固定在边坡上,并将防渗系统锚固在预制构件上;其既能加固边坡土体,又能实现防渗系统在陡峭边坡的锚固。
Prefabricated anti-seepage anchoring structure of steep rock slope and construction method
一种陡峭岩质边坡的预制防渗锚固结构及施工方法
ZHAI WENHUA (Autor:in) / LUO BIN (Autor:in) / FENG KUN (Autor:in) / QI CHANGQING (Autor:in) / ZHENG ZHONGHUA (Autor:in) / DING SHIWEN (Autor:in) / GAI YIMIN (Autor:in) / GUO ZHI (Autor:in)
01.08.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Prefabricated part joint anti-seepage construction method and anti-seepage structure
Europäisches Patentamt | 2022
|Rock steep slope road structure and construction method
Europäisches Patentamt | 2020
|Anti-water-seepage prefabricated slab construction method
Europäisches Patentamt | 2015
|Segmented grouting anchoring method for joint development high and steep rock slope
Europäisches Patentamt | 2022
|Rock-fill dam prefabricated panel anchoring structure and anchoring method