Assembling and positioning method for steel anchor beam space cable guide pipe
The embodiment of the invention relates to an assembling and positioning method for a steel anchor beam space cable guide pipe. The method comprises the steps that a platform is arranged on the hardened ground, and a first longitudinal and transverse datum line is arranged on the platform; according to the first longitudinal and transverse datum line on the platform, a tool structure is arranged on the platform, and the tool structure is used for assembling and positioning the cable guide pipe; a second longitudinal and transverse datum line is arranged on the wall plate, and the steel corbel is positioned according to the first longitudinal and transverse datum line on the platform and the second longitudinal and transverse datum line on the wall plate; the cable guide pipe is preliminarily arranged on the wall plate through a tool structure; determining a theoretical projection line of the cable conduit on the platform according to a preset deflection angle in the transverse bridge direction, carrying out baseline suspension wire on the intersecting opening of the cable conduit, and adjusting the position of the cable conduit in the horizontal direction through the tool structure so as to enable the baseline suspension wire to intersect with the theoretical projection line; and the position of the cable guide pipe in the vertical direction is adjusted according to the preset angle. According to the embodiment of the invention, the cable guide pipe is accurately positioned, and the efficiency is high.
本公开实施例是关于一种钢锚梁空间索导管的组装定位方法。该方法包括:在硬化地面上布设平台,并在平台上布置第一纵横基准线;根据平台上的第一纵横基准线,在平台上布设工装结构,工装结构用于索导管的组装定位;在壁板上进行布设第二纵横基准线,并根据平台上的第一纵横基准线和壁板上的第二纵横基准线定位钢牛腿;通过工装结构将索导管初步布设在壁板上;根据预设横桥向偏角确定索导管在平台上的理论投影线,并在索导管上相贯口上进行基线吊线,通过工装结构调整索导管在水平方向上的位置,以使基线吊线相交于理论投影线;根据预设角度调整索导管在竖直方向上的位置。本公开实施例对索导管的定位精确、效率高。
Assembling and positioning method for steel anchor beam space cable guide pipe
The embodiment of the invention relates to an assembling and positioning method for a steel anchor beam space cable guide pipe. The method comprises the steps that a platform is arranged on the hardened ground, and a first longitudinal and transverse datum line is arranged on the platform; according to the first longitudinal and transverse datum line on the platform, a tool structure is arranged on the platform, and the tool structure is used for assembling and positioning the cable guide pipe; a second longitudinal and transverse datum line is arranged on the wall plate, and the steel corbel is positioned according to the first longitudinal and transverse datum line on the platform and the second longitudinal and transverse datum line on the wall plate; the cable guide pipe is preliminarily arranged on the wall plate through a tool structure; determining a theoretical projection line of the cable conduit on the platform according to a preset deflection angle in the transverse bridge direction, carrying out baseline suspension wire on the intersecting opening of the cable conduit, and adjusting the position of the cable conduit in the horizontal direction through the tool structure so as to enable the baseline suspension wire to intersect with the theoretical projection line; and the position of the cable guide pipe in the vertical direction is adjusted according to the preset angle. According to the embodiment of the invention, the cable guide pipe is accurately positioned, and the efficiency is high.
本公开实施例是关于一种钢锚梁空间索导管的组装定位方法。该方法包括:在硬化地面上布设平台,并在平台上布置第一纵横基准线;根据平台上的第一纵横基准线,在平台上布设工装结构,工装结构用于索导管的组装定位;在壁板上进行布设第二纵横基准线,并根据平台上的第一纵横基准线和壁板上的第二纵横基准线定位钢牛腿;通过工装结构将索导管初步布设在壁板上;根据预设横桥向偏角确定索导管在平台上的理论投影线,并在索导管上相贯口上进行基线吊线,通过工装结构调整索导管在水平方向上的位置,以使基线吊线相交于理论投影线;根据预设角度调整索导管在竖直方向上的位置。本公开实施例对索导管的定位精确、效率高。
Assembling and positioning method for steel anchor beam space cable guide pipe
一种钢锚梁空间索导管的组装定位方法
ZHANG BIN (Autor:in) / GUO JITAO (Autor:in) / HOU HUANHUAN (Autor:in) / LI QIXING (Autor:in) / LIU KAIHUA (Autor:in) / WEI YANG (Autor:in)
18.08.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2022
|Accurate positioning and assembling method for beveled anchor pipe of anchor box
Europäisches Patentamt | 2023
|Positioning construction method for steel anchor beam of cable-stayed bridge
Europäisches Patentamt | 2024
|Prestressed steel anchor pipe and anchor cable tensioning device
Europäisches Patentamt | 2020
|