Double-row Larsen steel sheet pile construction method
The invention provides a double-row Larsen steel sheet pile construction method. The double-row Larsen steel sheet pile construction method comprises the following steps: (1) surveying, setting out and positioning; (2) driving a first lock catch by using piling equipment, then connecting the first lock catch and a Larsen steel sheet pile above the ground, and driving the Larsen steel sheet pile by using the piling equipment to obtain a double-row Larsen steel sheet pile structure unit; and the operation is repeated, the multiple structural units are connected, and the double-row Larsen steel sheet pile is obtained. According to the construction method for the double-row Larsen steel sheet piles, the structural units serve as construction units, the first lock catches are connected with the Larsen steel sheet piles, double-row stable connection of the double-row Larsen steel sheet piles is achieved, construction is convenient, and efficiency is high; the double-row Larsen steel sheet pile obtained after construction is high in integrity and better in supporting effect.
本发明提供一种双排拉森钢板桩施工方法,包括以下步骤:(1)测量放线定位;(2)使用打桩设备打入第一锁扣,然后在地面以上连接第一锁扣和拉森钢板桩,通过打桩设备打入拉森钢板桩,得到双排拉森钢板桩结构单元;重复操作,多个结构单元连接,得到双排拉森钢板桩。本发明双排拉森钢板桩施工方法以结构单元为施工单位,通过第一锁扣和拉森钢板桩的连接,实现双排拉森钢板桩的双排稳固连接,施工方便,效率高;施工后得到的双排拉森钢板桩,整体性强,支护效果更佳。
Double-row Larsen steel sheet pile construction method
The invention provides a double-row Larsen steel sheet pile construction method. The double-row Larsen steel sheet pile construction method comprises the following steps: (1) surveying, setting out and positioning; (2) driving a first lock catch by using piling equipment, then connecting the first lock catch and a Larsen steel sheet pile above the ground, and driving the Larsen steel sheet pile by using the piling equipment to obtain a double-row Larsen steel sheet pile structure unit; and the operation is repeated, the multiple structural units are connected, and the double-row Larsen steel sheet pile is obtained. According to the construction method for the double-row Larsen steel sheet piles, the structural units serve as construction units, the first lock catches are connected with the Larsen steel sheet piles, double-row stable connection of the double-row Larsen steel sheet piles is achieved, construction is convenient, and efficiency is high; the double-row Larsen steel sheet pile obtained after construction is high in integrity and better in supporting effect.
本发明提供一种双排拉森钢板桩施工方法,包括以下步骤:(1)测量放线定位;(2)使用打桩设备打入第一锁扣,然后在地面以上连接第一锁扣和拉森钢板桩,通过打桩设备打入拉森钢板桩,得到双排拉森钢板桩结构单元;重复操作,多个结构单元连接,得到双排拉森钢板桩。本发明双排拉森钢板桩施工方法以结构单元为施工单位,通过第一锁扣和拉森钢板桩的连接,实现双排拉森钢板桩的双排稳固连接,施工方便,效率高;施工后得到的双排拉森钢板桩,整体性强,支护效果更佳。
Double-row Larsen steel sheet pile construction method
一种双排拉森钢板桩施工方法
YU FEI (Autor:in) / XIE ZHAOYU (Autor:in) / HUANG JUN (Autor:in) / ZHAO PENGFEI (Autor:in) / XU SHENG (Autor:in) / CHEN JING (Autor:in) / DENG WEI (Autor:in) / HU KE (Autor:in) / LIU XIUZHEN (Autor:in) / WANG JIJUN (Autor:in)
22.08.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Larsen steel sheet pile suitable for low space and construction method of Larsen steel sheet pile
Europäisches Patentamt | 2024
|Larsen steel sheet pile and construction method thereof
Europäisches Patentamt | 2021
|