Construction process of external wall thermal insulation metal integrated plate
The invention relates to a construction technology of an external wall heat preservation metal integrated plate. The construction technology comprises the following steps that S1, a mounting frame is placed; s2, one metal plate is mounted on the mounting frame; s3, the metal plate is fixed on the mounting frame; s4, thermal insulation polystyrene foam filling; s5, filling with the elastic polyurethane aerogel; s6, the other metal plate is fixed on the mounting frame, and the step S3 is repeated; s7, the mounting frame is fixed to the outer wall; a user only needs to manually rotate a rotating rod in a first groove in a metal plate directly through a transverse rod, a clamping rod is driven by a rotating strip and a curved rod to be inserted into a first clamping groove in a grid plate, and then the grid plate can be fixed to an outer wall through bolts at the four corners of an installation frame, so that when the metal plate is installed on the grid plate, operation is simpler and more convenient, and the installation efficiency is improved. And the contact area between the clamping rods and the grid plate is increased while the installation work efficiency is improved, and the metal plate is installed more firmly.
本发明涉及外墙保温金属一体板施工工艺,包括以下步骤:S1、摆放好安装框;S2、在安装框上安装其中一块金属板;S3、在安装框上对金属板进行固定;S4、保温发泡胶填充;S5、弹性聚氨酯气凝胶填充;S6、在安装框上对另一块金属板固定,方法为重复步骤S3;S7、将安装框固定到外墙上;只需人工在金属板上的第一凹槽中直接利用横杆来转动转杆,通过转条和曲杆带动卡杆插进至网格板上的第一卡槽中,再通过安装框四个边角处的螺栓即可将其固定到外墙上,使得在网格板上安装金属板时,操作更加的简单、方便,提高安装工作效率的同时,卡杆增加了与网格板之间的接触面积,对金属板的安装也更加的牢固。
Construction process of external wall thermal insulation metal integrated plate
The invention relates to a construction technology of an external wall heat preservation metal integrated plate. The construction technology comprises the following steps that S1, a mounting frame is placed; s2, one metal plate is mounted on the mounting frame; s3, the metal plate is fixed on the mounting frame; s4, thermal insulation polystyrene foam filling; s5, filling with the elastic polyurethane aerogel; s6, the other metal plate is fixed on the mounting frame, and the step S3 is repeated; s7, the mounting frame is fixed to the outer wall; a user only needs to manually rotate a rotating rod in a first groove in a metal plate directly through a transverse rod, a clamping rod is driven by a rotating strip and a curved rod to be inserted into a first clamping groove in a grid plate, and then the grid plate can be fixed to an outer wall through bolts at the four corners of an installation frame, so that when the metal plate is installed on the grid plate, operation is simpler and more convenient, and the installation efficiency is improved. And the contact area between the clamping rods and the grid plate is increased while the installation work efficiency is improved, and the metal plate is installed more firmly.
本发明涉及外墙保温金属一体板施工工艺,包括以下步骤:S1、摆放好安装框;S2、在安装框上安装其中一块金属板;S3、在安装框上对金属板进行固定;S4、保温发泡胶填充;S5、弹性聚氨酯气凝胶填充;S6、在安装框上对另一块金属板固定,方法为重复步骤S3;S7、将安装框固定到外墙上;只需人工在金属板上的第一凹槽中直接利用横杆来转动转杆,通过转条和曲杆带动卡杆插进至网格板上的第一卡槽中,再通过安装框四个边角处的螺栓即可将其固定到外墙上,使得在网格板上安装金属板时,操作更加的简单、方便,提高安装工作效率的同时,卡杆增加了与网格板之间的接触面积,对金属板的安装也更加的牢固。
Construction process of external wall thermal insulation metal integrated plate
外墙保温金属一体板施工工艺
REN SHUDONG (Autor:in) / DING JIANHUI (Autor:in) / CHEN ZHONGWEI (Autor:in)
29.08.2023
Patent
Elektronische Ressource
Chinesisch
Outer wall external thermal insulation integrated construction method
Europäisches Patentamt | 2023
|External wall heat insulation and decoration integrated plate and construction process thereof
Europäisches Patentamt | 2023
|Anti-seepage integrated external wall thermal insulation decorative plate
Europäisches Patentamt | 2024
|Construction method for external wall insulation and decoration integrated plate
Europäisches Patentamt | 2020
|Construction method of external wall insulation and decoration integrated plate
Europäisches Patentamt | 2023
|