Construction method for top formwork of large-gradient sloping roof structure
A construction method for a top formwork of a large-gradient sloping roof structure is characterized by comprising the following steps that a, after a bottom formwork is installed, a plurality of positioning lines are popped up every 500 mm in the direction parallel to a ridge; b, after beam plate steel bars are bound, a plurality of vertical steel bars perpendicular to the beam plate are welded along the positioning line every 1-2 m; c, the vertical steel bars are marked according to the thickness of the beam plate and tightly connected through construction lines, and horizontal steel bars parallel to the beam plate are welded; and d, mounting and welding a plurality of angle steels on the horizontal steel bars, wherein the angle steels are arranged along the ridge parallel direction. The construction method for the top formwork of the large-gradient sloping roof structure has the advantages that the problem that the concrete pouring construction difficulty is large is solved, roof leakage is reduced, the construction efficiency is high, waste short steel bars are adopted for manufacturing and construction, environment friendliness is achieved, and the cost is reduced.
一种较大坡度斜屋面结构顶模板施工方法,其特征在于包括以下步骤:a、在底模板安装完成后,在平行于屋脊的方向每隔500mm弹若干定位线;b、在梁板钢筋绑扎完成后,沿着定位线每隔1‑2m焊接垂直于梁板的若干竖向钢筋;c、按照梁板厚度在竖向钢筋上标记并用施工线连紧,焊接平行于梁板的水平钢筋;d、在水平钢筋上安装焊接若干角钢,角钢沿屋脊平行方向设置。本发明的较大坡度斜屋面结构顶模板施工方法具有解决混凝土浇筑施工难度大的问题,减少屋面渗漏,施工效率高,采用废旧短钢筋制作施工,绿色环保和降低成本的优点。
Construction method for top formwork of large-gradient sloping roof structure
A construction method for a top formwork of a large-gradient sloping roof structure is characterized by comprising the following steps that a, after a bottom formwork is installed, a plurality of positioning lines are popped up every 500 mm in the direction parallel to a ridge; b, after beam plate steel bars are bound, a plurality of vertical steel bars perpendicular to the beam plate are welded along the positioning line every 1-2 m; c, the vertical steel bars are marked according to the thickness of the beam plate and tightly connected through construction lines, and horizontal steel bars parallel to the beam plate are welded; and d, mounting and welding a plurality of angle steels on the horizontal steel bars, wherein the angle steels are arranged along the ridge parallel direction. The construction method for the top formwork of the large-gradient sloping roof structure has the advantages that the problem that the concrete pouring construction difficulty is large is solved, roof leakage is reduced, the construction efficiency is high, waste short steel bars are adopted for manufacturing and construction, environment friendliness is achieved, and the cost is reduced.
一种较大坡度斜屋面结构顶模板施工方法,其特征在于包括以下步骤:a、在底模板安装完成后,在平行于屋脊的方向每隔500mm弹若干定位线;b、在梁板钢筋绑扎完成后,沿着定位线每隔1‑2m焊接垂直于梁板的若干竖向钢筋;c、按照梁板厚度在竖向钢筋上标记并用施工线连紧,焊接平行于梁板的水平钢筋;d、在水平钢筋上安装焊接若干角钢,角钢沿屋脊平行方向设置。本发明的较大坡度斜屋面结构顶模板施工方法具有解决混凝土浇筑施工难度大的问题,减少屋面渗漏,施工效率高,采用废旧短钢筋制作施工,绿色环保和降低成本的优点。
Construction method for top formwork of large-gradient sloping roof structure
一种较大坡度斜屋面结构顶模板施工方法
LIANG LIJUN (Autor:in) / LU BIN (Autor:in) / SHEN MING (Autor:in)
01.09.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Formwork structure for sloping roof and sloping roof construction method
Europäisches Patentamt | 2023
|Large-gradient cast-in-place concrete sloping roof formwork structure
Europäisches Patentamt | 2023
|Large building sloping roof formwork supporting system and construction method
Europäisches Patentamt | 2023
|Sloping roof formwork supporting frame and construction method thereof
Europäisches Patentamt | 2024
|