Installation construction method of spring vibration isolator
The invention provides a mounting construction method of a spring vibration isolator, which comprises the following steps: firstly, according to a preset construction positioning requirement, carrying out concrete pouring on a cushion layer, then carrying out pouring construction on a foundation box, laying an anti-sticking layer at the bottom of the foundation box, carrying out concrete pouring on a foundation block, and finally, carrying out installation construction on the spring vibration isolator. However, a plurality of slotted holes need to be reserved before pouring, the jacks are installed in the slotted holes, the foundation box and the foundation blocks are separated through the jacks, then the spring vibration isolators are installed, and after the spring vibration isolators are installed, the jacks are adjusted to enable the foundation blocks to be stably pressed on the spring vibration isolators. And then the jack is withdrawn, and installation construction of the spring vibration isolator is completed. According to the method, effective separation of the foundation block and the foundation box can be achieved, and then safe and accurate installation of the spring vibration isolator is guaranteed.
本发明提供了一种弹簧隔振器的安装施工方法,包括如下步骤:首先根据预设施工定位要求,对所述垫层进行混凝土浇筑,然后再进行所述基础箱浇筑施工,在所述基础箱底部铺设防粘层,对所述基础块进行混凝土浇筑,但在浇筑前需要预留多个槽孔,在所述槽孔内安装所述千斤顶,通过所述千斤顶将所述基础箱与所述基础块分离,再安装所述弹簧隔振器,所述弹簧隔振器安装完成后,调节所述千斤顶,使所述基础块稳定压到所述弹簧隔振器上,再撤离所述千斤顶,完成所述弹簧隔振器的安装施工。在本发明中,通过上述方法,能够实现所述基础块与所述基础箱的有效分离,进而保证了所述弹簧隔振器的安全精准安装。
Installation construction method of spring vibration isolator
The invention provides a mounting construction method of a spring vibration isolator, which comprises the following steps: firstly, according to a preset construction positioning requirement, carrying out concrete pouring on a cushion layer, then carrying out pouring construction on a foundation box, laying an anti-sticking layer at the bottom of the foundation box, carrying out concrete pouring on a foundation block, and finally, carrying out installation construction on the spring vibration isolator. However, a plurality of slotted holes need to be reserved before pouring, the jacks are installed in the slotted holes, the foundation box and the foundation blocks are separated through the jacks, then the spring vibration isolators are installed, and after the spring vibration isolators are installed, the jacks are adjusted to enable the foundation blocks to be stably pressed on the spring vibration isolators. And then the jack is withdrawn, and installation construction of the spring vibration isolator is completed. According to the method, effective separation of the foundation block and the foundation box can be achieved, and then safe and accurate installation of the spring vibration isolator is guaranteed.
本发明提供了一种弹簧隔振器的安装施工方法,包括如下步骤:首先根据预设施工定位要求,对所述垫层进行混凝土浇筑,然后再进行所述基础箱浇筑施工,在所述基础箱底部铺设防粘层,对所述基础块进行混凝土浇筑,但在浇筑前需要预留多个槽孔,在所述槽孔内安装所述千斤顶,通过所述千斤顶将所述基础箱与所述基础块分离,再安装所述弹簧隔振器,所述弹簧隔振器安装完成后,调节所述千斤顶,使所述基础块稳定压到所述弹簧隔振器上,再撤离所述千斤顶,完成所述弹簧隔振器的安装施工。在本发明中,通过上述方法,能够实现所述基础块与所述基础箱的有效分离,进而保证了所述弹簧隔振器的安全精准安装。
Installation construction method of spring vibration isolator
一种弹簧隔振器的安装施工方法
ZHAI CONGCONG (Autor:in) / LIU RAN (Autor:in) / ZHANG YAOLIN (Autor:in) / LI NINGNING (Autor:in) / GONG KEJUN (Autor:in) / JIANG DONGSHENG (Autor:in) / FENG LULU (Autor:in) / ZHANG HUAWEI (Autor:in) / WEI RENGUI (Autor:in)
05.09.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen