Construction method of modular mixed structure adopting plug-in type mixed nodes
The invention relates to a construction method of a modular mixed structure adopting plug-in type mixed nodes, belongs to the technical field of modular steel structure buildings, and solves the problems of low bearing capacity and poor anti-seismic property of modular structural members in the prior art. The method comprises the steps that 1, lower layer module units are arranged side by side, and positioning and leveling work is completed on the tops of lower column connecting joints and the tops of lower joint beams of the lower layer module units; 2, slurry is poured into a gap between every two adjacent wallboards; 3, the first horizontal connecting plate and the second horizontal connecting plate are welded; 4, slurry is poured into the lower connecting cylinder and the lower joint beam; 5, the module units of the upper layer are hoisted; and 6, repeating the steps 2-5, and upwards mounting the module units layer by layer. The upper and lower module unit nodes and the beams are fixed in an inserting grouting mode, so that the upper and lower wallboards are connected into a whole, and the stability and the anti-seismic property of the structure are improved.
本发明涉及一种采用插接式混合节点的模块化混合结构的施工方法,属于模块化钢结构建筑技术领域,解决了现有技术中模块结构构件承载力低、抗震性能较差的问题。本发明的步骤包括步骤1:将下层模块单元并排排放,下层模块单元的下柱连接节点的顶部和下节点梁的顶部完成定位找平工作;步骤2:向相邻两个墙板的缝隙内灌入浆料;步骤3:焊接第一水平连接板和第二水平连接板;步骤4:向下连接筒和下节点梁内灌入浆料;步骤5:吊装上一层模块单元;步骤6:重复步骤2~步骤5,逐层向上安装模块单元。本发明的上下模块单元节点和梁均采用插接灌浆方式固定,使得上下墙板连接为一个整体,提高了结构的稳定性和抗震性能。
Construction method of modular mixed structure adopting plug-in type mixed nodes
The invention relates to a construction method of a modular mixed structure adopting plug-in type mixed nodes, belongs to the technical field of modular steel structure buildings, and solves the problems of low bearing capacity and poor anti-seismic property of modular structural members in the prior art. The method comprises the steps that 1, lower layer module units are arranged side by side, and positioning and leveling work is completed on the tops of lower column connecting joints and the tops of lower joint beams of the lower layer module units; 2, slurry is poured into a gap between every two adjacent wallboards; 3, the first horizontal connecting plate and the second horizontal connecting plate are welded; 4, slurry is poured into the lower connecting cylinder and the lower joint beam; 5, the module units of the upper layer are hoisted; and 6, repeating the steps 2-5, and upwards mounting the module units layer by layer. The upper and lower module unit nodes and the beams are fixed in an inserting grouting mode, so that the upper and lower wallboards are connected into a whole, and the stability and the anti-seismic property of the structure are improved.
本发明涉及一种采用插接式混合节点的模块化混合结构的施工方法,属于模块化钢结构建筑技术领域,解决了现有技术中模块结构构件承载力低、抗震性能较差的问题。本发明的步骤包括步骤1:将下层模块单元并排排放,下层模块单元的下柱连接节点的顶部和下节点梁的顶部完成定位找平工作;步骤2:向相邻两个墙板的缝隙内灌入浆料;步骤3:焊接第一水平连接板和第二水平连接板;步骤4:向下连接筒和下节点梁内灌入浆料;步骤5:吊装上一层模块单元;步骤6:重复步骤2~步骤5,逐层向上安装模块单元。本发明的上下模块单元节点和梁均采用插接灌浆方式固定,使得上下墙板连接为一个整体,提高了结构的稳定性和抗震性能。
Construction method of modular mixed structure adopting plug-in type mixed nodes
一种采用插接式混合节点的模块化混合结构的施工方法
LOU NI (Autor:in) / PENG MINGYING (Autor:in) / QU KEXIN (Autor:in) / YI GUOHUI (Autor:in) / LIU CHANGSONG (Autor:in) / TIAN WENQIN (Autor:in) / REN LEMING (Autor:in)
12.09.2023
Patent
Elektronische Ressource
Chinesisch
Construction method of latticed underground diaphragm wall adopting pile type nodes
Europäisches Patentamt | 2023
|Pipeline construction method adopting bubble-mixed lightweight soil backfilling method