Formwork supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
The invention discloses a formwork supporting system for integral pouring of a beam plate and an L-shaped hanging plate at the beam bottom. The formwork supporting system solves the problem of how to construct a supporting structure of the formwork system for integral pouring of the beam plate and the L-shaped hanging plate below the beam plate. A pre-poured L-shaped hanging plate bottom formwork supporting cross beam (4) and an inner side clamping steel pipe (29) are arranged on the full framing (1) under a pre-poured concrete beam space (23), and the L-shaped hanging plate bottom formwork supporting cross beam (4) and an outer side clamping steel pipe (18) form a U-shaped space of a construction beam and a beam bottom L-shaped hanging plate. A beam and slab integrated pouring formwork system convenient to disassemble and assemble is constructed in the U-shaped space, and the integrally poured concrete space is divided into the following three areas including the horizontal plate pouring space (25) of the L-shaped hanging plate, the vertical plate pouring space (24) of the L-shaped hanging plate and the top end beam and slab pouring space; the segmented integral pouring process is coordinated and matched with the template supporting system, so that integral pouring is realized.
本发明公开了一种梁板与梁底L形挂板整体浇筑的模板支撑体系,解决了如何构筑梁板及其下的L形挂板的整体浇筑模板体系的支撑结构的问题;在预浇筑的混凝土梁空间(23)的正下方的满堂支架(1)上,设置有预浇筑的L形挂板底模板支撑横梁(4),内侧夹紧钢管(29)、L形挂板底模板支撑横梁(4)和外侧夹紧钢管(18)组成一个构筑梁和梁底L形挂板的U形空间,在该U形空间内构筑便于拆装的梁板一体化浇筑模板体系,将整体浇筑的混凝土空间分成以下三个区域,L形挂板的水平板浇筑空间(25)、L形挂板的竖直板浇筑空间(24)和顶端梁板浇筑空间;这种分段整体的浇筑工艺与上述的模板支撑体系协调配合,从而实现了整体浇筑。
Formwork supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
The invention discloses a formwork supporting system for integral pouring of a beam plate and an L-shaped hanging plate at the beam bottom. The formwork supporting system solves the problem of how to construct a supporting structure of the formwork system for integral pouring of the beam plate and the L-shaped hanging plate below the beam plate. A pre-poured L-shaped hanging plate bottom formwork supporting cross beam (4) and an inner side clamping steel pipe (29) are arranged on the full framing (1) under a pre-poured concrete beam space (23), and the L-shaped hanging plate bottom formwork supporting cross beam (4) and an outer side clamping steel pipe (18) form a U-shaped space of a construction beam and a beam bottom L-shaped hanging plate. A beam and slab integrated pouring formwork system convenient to disassemble and assemble is constructed in the U-shaped space, and the integrally poured concrete space is divided into the following three areas including the horizontal plate pouring space (25) of the L-shaped hanging plate, the vertical plate pouring space (24) of the L-shaped hanging plate and the top end beam and slab pouring space; the segmented integral pouring process is coordinated and matched with the template supporting system, so that integral pouring is realized.
本发明公开了一种梁板与梁底L形挂板整体浇筑的模板支撑体系,解决了如何构筑梁板及其下的L形挂板的整体浇筑模板体系的支撑结构的问题;在预浇筑的混凝土梁空间(23)的正下方的满堂支架(1)上,设置有预浇筑的L形挂板底模板支撑横梁(4),内侧夹紧钢管(29)、L形挂板底模板支撑横梁(4)和外侧夹紧钢管(18)组成一个构筑梁和梁底L形挂板的U形空间,在该U形空间内构筑便于拆装的梁板一体化浇筑模板体系,将整体浇筑的混凝土空间分成以下三个区域,L形挂板的水平板浇筑空间(25)、L形挂板的竖直板浇筑空间(24)和顶端梁板浇筑空间;这种分段整体的浇筑工艺与上述的模板支撑体系协调配合,从而实现了整体浇筑。
Formwork supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
梁板与梁底L形挂板整体浇筑的模板支撑体系
GENG QIUHONG (Autor:in) / LIU WEI (Autor:in) / WANG PU (Autor:in) / QIN WANJUN (Autor:in) / ZHAO XIN (Autor:in) / ZHAO RUIZE (Autor:in) / JI PANPAN (Autor:in) / JIAO YANG (Autor:in) / MA ZHANFEI (Autor:in) / HU NAN (Autor:in)
17.10.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Europäisches Patentamt | 2024
|Beam-containing building top plate bottom formwork supporting system
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2024
|Special-shaped concrete cross beam formwork bottom supporting device
Europäisches Patentamt | 2024
|