Construction method for dismantling elevated hanging basin supported by steel protection clamp
The invention discloses a construction method for dismantling an elevated hanging basin supported by a steel protection clamp, which comprises the following steps of: S01, before dismantling the elevated hanging basin, performing traffic dispersion, and performing peripheral protection measures in an on-bridge construction range and an under-bridge construction range; s02, the dismantling device is moved to a designated station, the dumper stops on one side of the dismantling device, and inspection and acceptance are ready before construction; and S03, the elevated hanging basins needing to be dismantled are clamped and fixed through the dismantling device, then the elevated hanging basins are moved to a dumper to be stacked in order, and dismantling work is completed. According to the construction method, preparatory work can be made before construction, safety in the construction process is ensured, damage to pedestrians or vehicles and the like in the dismantling process is avoided, clamping, lifting and stacking can be automatically conducted through the dismantling device in the dismantling process, operation is more convenient and simpler, meanwhile, construction efficiency is high, the speed is high, and the construction efficiency is improved. The construction period is shortened, and the traffic maintenance interference time is reduced.
本发明公开了一种钢护夹支撑高架挂盆拆除施工方法,包括以下步骤:S01:在进行高架挂盆拆除前,做好交通疏导,对桥上和桥下施工范围内做好周边防护措施;S02:将拆除装置移动至指定工位,自卸车停靠在拆除装置的一侧,施工前准备就绪检查验收;S03:通过拆除装置将需要拆除的高架挂盆进行夹紧固定,再移动至自卸车码放整齐,完成拆除工作。本发明通过上述施工方法,可在施工前做好准备工作,确保在施工过程中的安全性,避免在拆除过程中对行人或车辆等造成伤害,并且拆除过程中通过拆除装置可自动对其进行卡紧,抬升和码放,操作更加方便简单,同时施工效率高、速度快,缩短了施工工期,减少了交通维护干扰的时间。
Construction method for dismantling elevated hanging basin supported by steel protection clamp
The invention discloses a construction method for dismantling an elevated hanging basin supported by a steel protection clamp, which comprises the following steps of: S01, before dismantling the elevated hanging basin, performing traffic dispersion, and performing peripheral protection measures in an on-bridge construction range and an under-bridge construction range; s02, the dismantling device is moved to a designated station, the dumper stops on one side of the dismantling device, and inspection and acceptance are ready before construction; and S03, the elevated hanging basins needing to be dismantled are clamped and fixed through the dismantling device, then the elevated hanging basins are moved to a dumper to be stacked in order, and dismantling work is completed. According to the construction method, preparatory work can be made before construction, safety in the construction process is ensured, damage to pedestrians or vehicles and the like in the dismantling process is avoided, clamping, lifting and stacking can be automatically conducted through the dismantling device in the dismantling process, operation is more convenient and simpler, meanwhile, construction efficiency is high, the speed is high, and the construction efficiency is improved. The construction period is shortened, and the traffic maintenance interference time is reduced.
本发明公开了一种钢护夹支撑高架挂盆拆除施工方法,包括以下步骤:S01:在进行高架挂盆拆除前,做好交通疏导,对桥上和桥下施工范围内做好周边防护措施;S02:将拆除装置移动至指定工位,自卸车停靠在拆除装置的一侧,施工前准备就绪检查验收;S03:通过拆除装置将需要拆除的高架挂盆进行夹紧固定,再移动至自卸车码放整齐,完成拆除工作。本发明通过上述施工方法,可在施工前做好准备工作,确保在施工过程中的安全性,避免在拆除过程中对行人或车辆等造成伤害,并且拆除过程中通过拆除装置可自动对其进行卡紧,抬升和码放,操作更加方便简单,同时施工效率高、速度快,缩短了施工工期,减少了交通维护干扰的时间。
Construction method for dismantling elevated hanging basin supported by steel protection clamp
一种钢护夹支撑高架挂盆拆除施工方法
WANG WEI (Autor:in) / LI HUIRONG (Autor:in) / DOU DECUN (Autor:in) / WANG XIANGYU (Autor:in) / MAO YIFENG (Autor:in) / LI FEI (Autor:in) / ZHANG JINSHAN (Autor:in) / WANG XIAOXING (Autor:in) / BI HAN (Autor:in) / WANG JIANJUN (Autor:in)
10.11.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
/
B66F
HOISTING, LIFTING, HAULING, OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
,
Hub-, Verhol- oder Schubvorrichtungen, soweit nicht anderweitig vorgesehen, z.B. Vorrichtungen mit unmittelbarer Krafteinwirkung auf die Last
/
E04G
SCAFFOLDING
,
Baugerüste
Construction method for dismantling rhombic hanging basket