Operation viaduct stand column pier body dismantling construction method based on reserved column head
The invention relates to an operation viaduct stand column pier body dismantling construction method based on reserved column heads. The method comprises the steps that a lifting point is arranged on a steel cross beam, and a fixed pulley is installed; a water drill is adopted for drilling according to the marked hoisting hole positions, and opposite-penetrating round steel is installed to serve as hoisting points; mounting a rope saw guide wheel and cutting equipment at the marked cutting surface position, and cutting a first cutting surface; mounting a steel wire rope and a chain hoist, and hanging the steel wire rope after the folding arm crane is in place; mounting a rope saw guide wheel and cutting equipment, and cutting a second cutter cutting surface; slowly moving the cutting block out of the plane position of the original pier body through synchronous matching of the chain hoist and the folding arm crane, and then slowly lowering the cutting block to the ground; and repeating the previous steps until the upright post is removed. According to the method, the problem that the old stand column cannot be dismounted by using large-scale mechanical equipment in a narrow space and the difficulty is high can be safely and effectively solved under the condition that the reserved column head and the underpinning steel frame are not collided in a limited space through manual cooperation of a hand-drive block, a rope saw, a folding-arm crane and other machines and tools.
本发明涉及一种基于保留柱头的运营高架桥梁立柱墩身拆除施工方法,其步骤为:在钢横梁设置吊点并安装定滑轮;按标记好的吊装孔位置采用水钻开孔,安装对穿圆钢做吊点;在标记好的切割面位置安装绳锯导向轮和切割设备,切割第一刀切割面;安装钢丝绳、手动葫芦,折臂吊就位后挂钢丝绳;安装绳锯导向轮和切割设备,切割第二刀切割面;通过手动葫芦和折臂吊同步配合,将切割块缓慢移出原墩身平面位置,然后缓慢下放至地面;重复前面步骤直至立柱拆除完成。本发明通过人工配合手动葫芦、绳锯、折臂吊等机具,在有限空间内不碰撞保留柱头和托换钢架的情况下,可安全有效解决狭小空间内无法使用大型机械设备拆除老立柱难度大的问题。
Operation viaduct stand column pier body dismantling construction method based on reserved column head
The invention relates to an operation viaduct stand column pier body dismantling construction method based on reserved column heads. The method comprises the steps that a lifting point is arranged on a steel cross beam, and a fixed pulley is installed; a water drill is adopted for drilling according to the marked hoisting hole positions, and opposite-penetrating round steel is installed to serve as hoisting points; mounting a rope saw guide wheel and cutting equipment at the marked cutting surface position, and cutting a first cutting surface; mounting a steel wire rope and a chain hoist, and hanging the steel wire rope after the folding arm crane is in place; mounting a rope saw guide wheel and cutting equipment, and cutting a second cutter cutting surface; slowly moving the cutting block out of the plane position of the original pier body through synchronous matching of the chain hoist and the folding arm crane, and then slowly lowering the cutting block to the ground; and repeating the previous steps until the upright post is removed. According to the method, the problem that the old stand column cannot be dismounted by using large-scale mechanical equipment in a narrow space and the difficulty is high can be safely and effectively solved under the condition that the reserved column head and the underpinning steel frame are not collided in a limited space through manual cooperation of a hand-drive block, a rope saw, a folding-arm crane and other machines and tools.
本发明涉及一种基于保留柱头的运营高架桥梁立柱墩身拆除施工方法,其步骤为:在钢横梁设置吊点并安装定滑轮;按标记好的吊装孔位置采用水钻开孔,安装对穿圆钢做吊点;在标记好的切割面位置安装绳锯导向轮和切割设备,切割第一刀切割面;安装钢丝绳、手动葫芦,折臂吊就位后挂钢丝绳;安装绳锯导向轮和切割设备,切割第二刀切割面;通过手动葫芦和折臂吊同步配合,将切割块缓慢移出原墩身平面位置,然后缓慢下放至地面;重复前面步骤直至立柱拆除完成。本发明通过人工配合手动葫芦、绳锯、折臂吊等机具,在有限空间内不碰撞保留柱头和托换钢架的情况下,可安全有效解决狭小空间内无法使用大型机械设备拆除老立柱难度大的问题。
Operation viaduct stand column pier body dismantling construction method based on reserved column head
基于保留柱头的运营高架桥梁立柱墩身拆除施工方法
LIAN HAIJIAN (Autor:in) / KIM DONG-HWA (Autor:in) / ZHANG ZHENHUA (Autor:in) / JIA SHUAIFENG (Autor:in) / HUANG JING (Autor:in) / HUANG WEI (Autor:in)
28.11.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Underpinning transformation method for dismantling operation viaduct stand column
Europäisches Patentamt | 2023
|Method for dismantling pier stud bent cap with upper structure reserved on viaduct
Europäisches Patentamt | 2023
|Bridge pier column construction steel bar dismantling method
Europäisches Patentamt | 2022
|