Construction method of underwater non-dispersible concrete long spiral expanded-base cast-in-place pile
The invention discloses a construction method of an underwater non-dispersible concrete long spiral bottom-expanded cast-in-place pile, and belongs to the field of concrete pile foundation construction.The construction method comprises the following steps that S1, a pile position is measured and arranged, and a reinforcement cage and a pile casing are prepared; s2, a construction platform is erected, and the pile casing is driven into a riverbed or a seabed; s3, drilling holes; s4, expanding the bottom; s5, the reinforcement cage is pressed into the pile casing, and underwater non-dispersible concrete is pumped; and S6, after the pile is formed, maintenance is conducted, the pile casing is pulled out, and quality inspection is conducted on the cast-in-place pile. The construction method is simple, concrete can be prevented from being dispersed when encountering water, the construction quality of the underwater cast-in-place concrete pile is guaranteed, the pile foundation bearing capacity is enhanced, the pile body length is shortened, the engineering cost is reduced, and good environment friendliness is achieved.
本发明公开了一种水下不分散混凝土长螺旋扩底灌注桩施工方法,属于混凝土桩基施工领域,该施工方法包括如下步骤:S1:测设桩位,准备钢筋笼和护筒;S2:架设施工平台,将护筒打入至河床或海床;S3钻孔;S4:扩底;S5:将钢筋笼压入护筒,泵送水下不分散混凝土;S6:成桩后进行养护,抽出护筒,并对灌注桩进行质量检验。本发明施工方法简单,能防止混凝土遇水分散,保证水下混凝土灌注桩的施工质量,增强桩基承载力,缩短桩身长度降低工程造价,并且具有良好的环境友好性。
Construction method of underwater non-dispersible concrete long spiral expanded-base cast-in-place pile
The invention discloses a construction method of an underwater non-dispersible concrete long spiral bottom-expanded cast-in-place pile, and belongs to the field of concrete pile foundation construction.The construction method comprises the following steps that S1, a pile position is measured and arranged, and a reinforcement cage and a pile casing are prepared; s2, a construction platform is erected, and the pile casing is driven into a riverbed or a seabed; s3, drilling holes; s4, expanding the bottom; s5, the reinforcement cage is pressed into the pile casing, and underwater non-dispersible concrete is pumped; and S6, after the pile is formed, maintenance is conducted, the pile casing is pulled out, and quality inspection is conducted on the cast-in-place pile. The construction method is simple, concrete can be prevented from being dispersed when encountering water, the construction quality of the underwater cast-in-place concrete pile is guaranteed, the pile foundation bearing capacity is enhanced, the pile body length is shortened, the engineering cost is reduced, and good environment friendliness is achieved.
本发明公开了一种水下不分散混凝土长螺旋扩底灌注桩施工方法,属于混凝土桩基施工领域,该施工方法包括如下步骤:S1:测设桩位,准备钢筋笼和护筒;S2:架设施工平台,将护筒打入至河床或海床;S3钻孔;S4:扩底;S5:将钢筋笼压入护筒,泵送水下不分散混凝土;S6:成桩后进行养护,抽出护筒,并对灌注桩进行质量检验。本发明施工方法简单,能防止混凝土遇水分散,保证水下混凝土灌注桩的施工质量,增强桩基承载力,缩短桩身长度降低工程造价,并且具有良好的环境友好性。
Construction method of underwater non-dispersible concrete long spiral expanded-base cast-in-place pile
一种水下不分散混凝土长螺旋扩底灌注桩施工方法
NIE JILI (Autor:in) / NIE KAI (Autor:in) / ZHENG JIANPING (Autor:in) / WU PENGPENG (Autor:in) / LI ZHICHAO (Autor:in) / ZHOU SHUANGXI (Autor:in) / XU HAO (Autor:in)
08.12.2023
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2022
|CAST-IN-PLACE CONCRETE PILE CONSTRUCTION METHOD AND CAST-IN-PLACE CONCRETE PILE
Europäisches Patentamt | 2019
|Long spiral drilling machine and cast-in-place pile construction method
Europäisches Patentamt | 2021
|CAST-IN-PLACE CONCRETE PILE CONSTRUCTION METHOD AND CAST-IN-PLACE CONCRETE PILE
Europäisches Patentamt | 2019
|