Construction method and system for high slope roadbed pile plate retaining wall
The invention relates to the technical field of retaining wall construction equipment, in particular to a high slope roadbed pile plate retaining wall construction method and system.The high slope roadbed pile plate retaining wall construction system comprises a supporting base, a lifting assembly, an adjusting assembly and a clamping assembly, the lifting assembly is installed on the supporting base, and the adjusting assembly is installed at the moving end of the lifting assembly; the lifting assembly is used for controlling the adjusting assembly to move up and down, the clamping assembly is installed at the moving end of the adjusting assembly, the adjusting assembly is used for controlling the clamping assembly to move transversely, the clamping assembly is used for fixing the end of a reinforcing steel bar, and the clamping assembly comprises a sliding frame, a lower clamping plate, a sliding rod, a top plate and an upper clamping plate. According to the purpose, steel bars of different specifications can be conveniently clamped, the ends can be conveniently clamped, the positions of the steel bars are adjusted through an adjusting assembly and a lifting assembly, manpower and material resources are saved, and the working efficiency is improved.
本发明涉及挡墙施工设备技术领域,具体涉及一种高边坡路基桩板挡墙施工方法及系统,包括支撑座、升降组件、调节组件和夹持组件,所述升降组件安装在所述支撑座上,所述调节组件安装在所述升降组件的移动端上,所述升降组件用于控制调节组件上下移动,所述夹持组件安装在所述调节组件的移动端上,所述调节组件用于控制所述夹持组件横向移动,所述夹持组件用于固定钢筋的端头,所述夹持组件包括滑动框、下夹持板、滑动杆、顶板和上夹持板;其目的是:便于将不同规格的钢筋进行夹持,且对端头夹持方便,利用调节组件和升降组件调整钢筋的位置,节省了人力物力,提高了工作效率。
Construction method and system for high slope roadbed pile plate retaining wall
The invention relates to the technical field of retaining wall construction equipment, in particular to a high slope roadbed pile plate retaining wall construction method and system.The high slope roadbed pile plate retaining wall construction system comprises a supporting base, a lifting assembly, an adjusting assembly and a clamping assembly, the lifting assembly is installed on the supporting base, and the adjusting assembly is installed at the moving end of the lifting assembly; the lifting assembly is used for controlling the adjusting assembly to move up and down, the clamping assembly is installed at the moving end of the adjusting assembly, the adjusting assembly is used for controlling the clamping assembly to move transversely, the clamping assembly is used for fixing the end of a reinforcing steel bar, and the clamping assembly comprises a sliding frame, a lower clamping plate, a sliding rod, a top plate and an upper clamping plate. According to the purpose, steel bars of different specifications can be conveniently clamped, the ends can be conveniently clamped, the positions of the steel bars are adjusted through an adjusting assembly and a lifting assembly, manpower and material resources are saved, and the working efficiency is improved.
本发明涉及挡墙施工设备技术领域,具体涉及一种高边坡路基桩板挡墙施工方法及系统,包括支撑座、升降组件、调节组件和夹持组件,所述升降组件安装在所述支撑座上,所述调节组件安装在所述升降组件的移动端上,所述升降组件用于控制调节组件上下移动,所述夹持组件安装在所述调节组件的移动端上,所述调节组件用于控制所述夹持组件横向移动,所述夹持组件用于固定钢筋的端头,所述夹持组件包括滑动框、下夹持板、滑动杆、顶板和上夹持板;其目的是:便于将不同规格的钢筋进行夹持,且对端头夹持方便,利用调节组件和升降组件调整钢筋的位置,节省了人力物力,提高了工作效率。
Construction method and system for high slope roadbed pile plate retaining wall
一种高边坡路基桩板挡墙施工方法及系统
WANG XIAOLONG (Autor:in) / XIE CHAO (Autor:in) / LIU LANJIE (Autor:in) / MAO YUNHUA (Autor:in) / DUAN HUI (Autor:in)
22.12.2023
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2022
|Pile-type Retaining wall structure for railway roadbed maintenance
Europäisches Patentamt | 2022
|Foam concrete slope trimming pile plate type broadened roadbed construction method
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2023
|