Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Half-open and half-dark tunnel construction method and protection structure
The invention relates to a half-open and half-dark tunnel construction method and a protection structure, belongs to the technical field of highway tunnel design and construction, and solves the problems of long construction time and unstable quality caused by cast-in-place retaining wall in an existing construction method. The semi-open and semi-concealed construction method for the tunnel comprises the following steps: excavating and reinforcing a side slope, constructing a pile foundation and prefabricating an assembly type retaining wall, mounting the assembly type retaining wall, constructing a large pipe shed and a cover arch at a concealed hole section, constructing an advance support and a protective arch at an open cut tunnel section, backfilling an arch crown, excavating a concealed hole and sealing a support, excavating a tunnel bottom, and replacing and supporting the tunnel bottom. The excavation volume of the highway tunnel crossing the steep road section is effectively reduced, and the safety of half-bright and half-dark construction of the highway tunnel is improved.
本发明涉及一种半明半暗隧道施工方法及防护结构,属于公路隧道设计施工技术领域,解决了现有施工方法现场浇筑挡墙,导致施工时间长、质量不稳定的问题。隧道半明半暗施工方法,包括如下步骤:边坡开挖及加固→施作桩基以及预制装配式挡墙→安装装配式挡墙→施作暗洞段大管棚及套拱→施作明洞段超前支护和护拱→拱顶回填→暗洞开挖及封闭支护→开挖隧底,进行隧底换填及支护。本发明有效降低了公路隧道穿越陡峭路段开挖量,并提高了公路隧道半明半暗施工安全性。
Half-open and half-dark tunnel construction method and protection structure
The invention relates to a half-open and half-dark tunnel construction method and a protection structure, belongs to the technical field of highway tunnel design and construction, and solves the problems of long construction time and unstable quality caused by cast-in-place retaining wall in an existing construction method. The semi-open and semi-concealed construction method for the tunnel comprises the following steps: excavating and reinforcing a side slope, constructing a pile foundation and prefabricating an assembly type retaining wall, mounting the assembly type retaining wall, constructing a large pipe shed and a cover arch at a concealed hole section, constructing an advance support and a protective arch at an open cut tunnel section, backfilling an arch crown, excavating a concealed hole and sealing a support, excavating a tunnel bottom, and replacing and supporting the tunnel bottom. The excavation volume of the highway tunnel crossing the steep road section is effectively reduced, and the safety of half-bright and half-dark construction of the highway tunnel is improved.
本发明涉及一种半明半暗隧道施工方法及防护结构,属于公路隧道设计施工技术领域,解决了现有施工方法现场浇筑挡墙,导致施工时间长、质量不稳定的问题。隧道半明半暗施工方法,包括如下步骤:边坡开挖及加固→施作桩基以及预制装配式挡墙→安装装配式挡墙→施作暗洞段大管棚及套拱→施作明洞段超前支护和护拱→拱顶回填→暗洞开挖及封闭支护→开挖隧底,进行隧底换填及支护。本发明有效降低了公路隧道穿越陡峭路段开挖量,并提高了公路隧道半明半暗施工安全性。
Half-open and half-dark tunnel construction method and protection structure
一种半明半暗隧道施工方法及防护结构
WANG GUOQING (Autor:in) / WANG CHAOJIE (Autor:in) / WANG JINGLI (Autor:in) / LI NING (Autor:in) / XU RUINING (Autor:in) / JI QIANG (Autor:in) / ZHAO WEIJUAN (Autor:in) / ZHAO MENG (Autor:in) / ZHANG XIN (Autor:in) / FENG ZHIHUA (Autor:in)
26.12.2023
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2022
|Half-open and half-hidden tunnel entering construction method for unsymmetrical pressure tunnel
Europäisches Patentamt | 2023
|Half-roadbed and half-tunnel road structure and construction method thereof
Europäisches Patentamt | 2020
|Study of the Mechanics Behavior of Small Net Distance Half-Open and Half-Hidden Structure Tunnel
Trans Tech Publications | 2011
|Study of the Mechanics Behavior of Small Net Distance Half-Open and Half-Hidden Structure Tunnel
British Library Conference Proceedings | 2011
|