Construction method for reinforcing, lifting and transforming existing riverway sluice
The invention discloses a construction method for reinforcing, lifting and transforming an existing riverway sluice. The reinforcing and transforming comprises the steps that a sluice chamber and a wing wall of the existing sluice are dismantled, an original sluice culvert is reserved, a newly-built sluice chamber is connected with the original sluice culvert, and a newly-built wing wall is connected with the sluice. When the old water gate chamber is dismantled, the original gate culvert and the gate opening channel bottom anti-seepage blanket section need to be protected to be complete in structure, the original channel bottom anti-seepage blanket section needs to be repaired if damaged, the original channel bottom blanket needs to be smoothly connected with a newly-built section, and a base is replaced and filled. The method can solve the problem of repair and transformation construction of an existing old water gate.
本发明公开了一种既有河道水闸加固提升改造施工方法,加固改造是拆除既有水闸的闸室和翼墙,保留原闸涵,新建闸室与原闸涵连接,新建翼墙与水闸连接。所述老旧水闸闸室拆除时,应保护原闸涵和闸口渠底防渗铺盖段结构完整,原渠底防渗铺盖段若有破损应进行修补,原渠底铺盖应于新建段平顺连接,并对基底进行换填处理。本发明可以解决现有的老旧水闸进行修复改造施工的问题。
Construction method for reinforcing, lifting and transforming existing riverway sluice
The invention discloses a construction method for reinforcing, lifting and transforming an existing riverway sluice. The reinforcing and transforming comprises the steps that a sluice chamber and a wing wall of the existing sluice are dismantled, an original sluice culvert is reserved, a newly-built sluice chamber is connected with the original sluice culvert, and a newly-built wing wall is connected with the sluice. When the old water gate chamber is dismantled, the original gate culvert and the gate opening channel bottom anti-seepage blanket section need to be protected to be complete in structure, the original channel bottom anti-seepage blanket section needs to be repaired if damaged, the original channel bottom blanket needs to be smoothly connected with a newly-built section, and a base is replaced and filled. The method can solve the problem of repair and transformation construction of an existing old water gate.
本发明公开了一种既有河道水闸加固提升改造施工方法,加固改造是拆除既有水闸的闸室和翼墙,保留原闸涵,新建闸室与原闸涵连接,新建翼墙与水闸连接。所述老旧水闸闸室拆除时,应保护原闸涵和闸口渠底防渗铺盖段结构完整,原渠底防渗铺盖段若有破损应进行修补,原渠底铺盖应于新建段平顺连接,并对基底进行换填处理。本发明可以解决现有的老旧水闸进行修复改造施工的问题。
Construction method for reinforcing, lifting and transforming existing riverway sluice
一种既有河道水闸加固提升改造施工方法
SUN JIANJIE (Autor:in) / WANG SIJIE (Autor:in) / HUANG XIANWEN (Autor:in) / HUANG XUEJI (Autor:in) / ZHU YUDONG (Autor:in) / HE FAN (Autor:in) / YE YUQIANG (Autor:in)
02.02.2024
Patent
Elektronische Ressource
Chinesisch
Construction method for reinforcing and transforming existing building structure
Europäisches Patentamt | 2024
|Construction method for reinforcing desilting retaining wall of urban landscape riverway
Europäisches Patentamt | 2021
|