A track mechanism comprises a first limiting plate and a second limiting plate and is provided with an opening and an inner cavity which communicate with each other, the first limiting plate and the second limiting plate are arranged at an interval to form the opening, and the inner cavity and the opening extend in the first direction; the truss is used for installing construction devices; the mounting seat is arranged on the truss, the rotating rod is rotatably arranged on the mounting seat, and the first limiting roller and the second limiting roller are coaxially arranged on the rotating rod. When the rotating rod drives the axis of the first limiting roller and the axis of the second limiting roller to rotate to the first direction, the first limiting roller and the second limiting roller are used for entering the inner cavity through the opening. When the rotating rod drives the axis of the first limiting roller and the axis of the second limiting roller to rotate to be perpendicular to the first direction, the first limiting roller is used for being in rolling fit with the first limiting plate, and the second limiting roller is used for being in rolling fit with the second limiting plate. When the construction equipment for the overflow dam is mounted or dismounted, the process is simple, and operation is convenient.
本申请涉及一种用于溢流坝的施工设备,轨道机构包括第一限位板和第二限位板并设有相互连通的开口和内腔,第一限位板和第二限位板间隔设置以形成开口,内腔和开口均沿第一方向延伸设置;桁架用于安装施工装置;安装座设于桁架,转动杆可转动地设于安装座,第一限位辊和第二限位辊同轴设置于转动杆上。转动杆带动第一限位辊的轴线和第二限位辊的轴线转动至第一方向时,第一限位辊和第二限位辊均用于通过开口进入内腔;转动杆带动第一限位辊的轴线和第二限位辊的轴线转动至与第一方向垂直时,第一限位辊用于与第一限位板滚动配合,第二限位辊用于与第二限位板滚动配合。上述用于溢流坝的施工设备在安装或拆卸施工装置时,过程简单且便于操作。
Construction equipment for overflow dam
A track mechanism comprises a first limiting plate and a second limiting plate and is provided with an opening and an inner cavity which communicate with each other, the first limiting plate and the second limiting plate are arranged at an interval to form the opening, and the inner cavity and the opening extend in the first direction; the truss is used for installing construction devices; the mounting seat is arranged on the truss, the rotating rod is rotatably arranged on the mounting seat, and the first limiting roller and the second limiting roller are coaxially arranged on the rotating rod. When the rotating rod drives the axis of the first limiting roller and the axis of the second limiting roller to rotate to the first direction, the first limiting roller and the second limiting roller are used for entering the inner cavity through the opening. When the rotating rod drives the axis of the first limiting roller and the axis of the second limiting roller to rotate to be perpendicular to the first direction, the first limiting roller is used for being in rolling fit with the first limiting plate, and the second limiting roller is used for being in rolling fit with the second limiting plate. When the construction equipment for the overflow dam is mounted or dismounted, the process is simple, and operation is convenient.
本申请涉及一种用于溢流坝的施工设备,轨道机构包括第一限位板和第二限位板并设有相互连通的开口和内腔,第一限位板和第二限位板间隔设置以形成开口,内腔和开口均沿第一方向延伸设置;桁架用于安装施工装置;安装座设于桁架,转动杆可转动地设于安装座,第一限位辊和第二限位辊同轴设置于转动杆上。转动杆带动第一限位辊的轴线和第二限位辊的轴线转动至第一方向时,第一限位辊和第二限位辊均用于通过开口进入内腔;转动杆带动第一限位辊的轴线和第二限位辊的轴线转动至与第一方向垂直时,第一限位辊用于与第一限位板滚动配合,第二限位辊用于与第二限位板滚动配合。上述用于溢流坝的施工设备在安装或拆卸施工装置时,过程简单且便于操作。
Construction equipment for overflow dam
用于溢流坝的施工设备
ZHU WENBIN (Autor:in) / ZHAO WEIGUO (Autor:in) / LU JUNTAO (Autor:in) / DENG QIONGXING (Autor:in) / ZHONG LANG (Autor:in) / XIAO MENG (Autor:in) / YING PENGTAO (Autor:in) / SHI YUNLI (Autor:in) / WANG ZHI (Autor:in) / HUANG HECHENG (Autor:in)
19.03.2024
Patent
Elektronische Ressource
Chinesisch
Dam overflow surface concrete construction equipment and construction method
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2021
|Roof overflow structure of curtain wall and construction method of roof overflow structure
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2023
|