Earthwork foundation pit layered excavation method
The invention provides an earthwork foundation pit layered excavation method. The earthwork foundation pit layered excavation method comprises the following construction modes: a layered excavation mode: according to design and engineering practice, the whole earthwork excavation is divided into a plurality of stages, each stage is divided into a plurality of layers, and the excavation thickness value of each layer is 1-2m; according to the earthwork outward transportation mode, a backhoe excavator and a long-arm excavator are matched for earth cutting in the out-pit operation, and a truck and a dump truck are matched for outward transportation of the excavated earthwork. The earthwork foundation pit layered excavation method provided by the invention is convenient to use, and by adopting the layered excavation method, an intelligent monitoring system, environmental protection measures, a pit bottom reinforcement technology and construction simulation and progress management technical means, the efficiency and safety of foundation pit engineering excavation are greatly improved, the environmental pollution is reduced, the foundation bearing capacity is improved, and the construction cost is reduced. And resource allocation is optimized, construction quality and safety are ensured, and a stable foundation is provided for subsequent engineering construction.
本发明提供一种土方基坑分层开挖方法。所述土方基坑分层开挖方法包括以下施工方式:分层开挖方式:根据设计及工程实际,将土方开挖整体分为若干阶段,每个阶段内分为若干层,每层开挖厚度取值在1m至2m;土方外运方式:坑外作业采用反铲挖掘机与长臂式挖掘机配合挖土、装车和自卸汽车进行配合对挖出的土方进行外运。本发明提供的土方基坑分层开挖方法具有使用方便,通过采用分层开挖方法、智能监控系统、环保措施、坑底加固技术、施工模拟和进度管理技术手段,大大提高了基坑工程开挖的效率和安全性,降低了环境污染,提高了地基承载力,优化了资源配置,确保了施工质量与安全,为后续工程建设提供了稳定的基础的优点。
Earthwork foundation pit layered excavation method
The invention provides an earthwork foundation pit layered excavation method. The earthwork foundation pit layered excavation method comprises the following construction modes: a layered excavation mode: according to design and engineering practice, the whole earthwork excavation is divided into a plurality of stages, each stage is divided into a plurality of layers, and the excavation thickness value of each layer is 1-2m; according to the earthwork outward transportation mode, a backhoe excavator and a long-arm excavator are matched for earth cutting in the out-pit operation, and a truck and a dump truck are matched for outward transportation of the excavated earthwork. The earthwork foundation pit layered excavation method provided by the invention is convenient to use, and by adopting the layered excavation method, an intelligent monitoring system, environmental protection measures, a pit bottom reinforcement technology and construction simulation and progress management technical means, the efficiency and safety of foundation pit engineering excavation are greatly improved, the environmental pollution is reduced, the foundation bearing capacity is improved, and the construction cost is reduced. And resource allocation is optimized, construction quality and safety are ensured, and a stable foundation is provided for subsequent engineering construction.
本发明提供一种土方基坑分层开挖方法。所述土方基坑分层开挖方法包括以下施工方式:分层开挖方式:根据设计及工程实际,将土方开挖整体分为若干阶段,每个阶段内分为若干层,每层开挖厚度取值在1m至2m;土方外运方式:坑外作业采用反铲挖掘机与长臂式挖掘机配合挖土、装车和自卸汽车进行配合对挖出的土方进行外运。本发明提供的土方基坑分层开挖方法具有使用方便,通过采用分层开挖方法、智能监控系统、环保措施、坑底加固技术、施工模拟和进度管理技术手段,大大提高了基坑工程开挖的效率和安全性,降低了环境污染,提高了地基承载力,优化了资源配置,确保了施工质量与安全,为后续工程建设提供了稳定的基础的优点。
Earthwork foundation pit layered excavation method
一种土方基坑分层开挖方法
YIN HEJUN (Autor:in) / LIU WEI (Autor:in) / JING YUTING (Autor:in) / YUAN JINBO (Autor:in) / LI HANG (Autor:in) / WANG ZHENXING (Autor:in) / LI XIANGDA (Autor:in) / ZHANG YONG (Autor:in) / HU LIANCHAO (Autor:in) / SUN LIUKUI (Autor:in)
26.03.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
/
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
/
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
Inner support foundation pit site earthwork layered excavation construction method
Europäisches Patentamt | 2023
|Deep foundation pit earthwork transportation device and excavation method
Europäisches Patentamt | 2024
|