Early-dismantling supporting structure for top plate
The invention provides a top plate early-dismantling supporting structure. The top plate early-dismantling supporting structure comprises a supporting body making contact with a concrete top plate, a face plate and a main edge square pipe. The panel is mounted on the main edge square tube; an adjusting lead screw oil support is mounted at the bottom of the supporting main body; a main ridge height adjusting piece used for adjusting the height of the main ridge square pipe is installed on the side face of the top of the supporting body. When concrete reaches a certain age and does not meet the requirement for formwork removal strength, the top plate formwork is removed in advance, and therefore waiting time is saved. The top plate support is not dismantled and serves as a concrete plate bearing supporting point, the turnover frequency of a top plate formwork is increased, the use amount of the formwork is reduced, the engineering cost is reduced, and economic benefits are improved.
本发明提供了一种顶板早拆支撑结构,包括:与混凝土顶板接触的支撑主体、面板和主楞方管;所述面板安装在所述主楞方管上;所述支撑主体的底部安装有调节丝杠油托;所述支撑主体的顶部侧面安装有用于调节主楞方管高度的主楞调高件。通过本发明在混凝土达到一定龄期未达到拆模强度要求时提前将顶板模板拆除,从而节省等待时间。本发明顶板支撑不拆除,作为混凝土板承重支撑点,提高顶板模板周转次数,降低模板使用量,降低工程成本,提高经济效益。
Early-dismantling supporting structure for top plate
The invention provides a top plate early-dismantling supporting structure. The top plate early-dismantling supporting structure comprises a supporting body making contact with a concrete top plate, a face plate and a main edge square pipe. The panel is mounted on the main edge square tube; an adjusting lead screw oil support is mounted at the bottom of the supporting main body; a main ridge height adjusting piece used for adjusting the height of the main ridge square pipe is installed on the side face of the top of the supporting body. When concrete reaches a certain age and does not meet the requirement for formwork removal strength, the top plate formwork is removed in advance, and therefore waiting time is saved. The top plate support is not dismantled and serves as a concrete plate bearing supporting point, the turnover frequency of a top plate formwork is increased, the use amount of the formwork is reduced, the engineering cost is reduced, and economic benefits are improved.
本发明提供了一种顶板早拆支撑结构,包括:与混凝土顶板接触的支撑主体、面板和主楞方管;所述面板安装在所述主楞方管上;所述支撑主体的底部安装有调节丝杠油托;所述支撑主体的顶部侧面安装有用于调节主楞方管高度的主楞调高件。通过本发明在混凝土达到一定龄期未达到拆模强度要求时提前将顶板模板拆除,从而节省等待时间。本发明顶板支撑不拆除,作为混凝土板承重支撑点,提高顶板模板周转次数,降低模板使用量,降低工程成本,提高经济效益。
Early-dismantling supporting structure for top plate
一种顶板早拆支撑结构
HUI YUQING (Autor:in)
12.04.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2022
|Constructional engineering early-dismantling supporting equipment
Europäisches Patentamt | 2021
|