Method for installing special-shaped prefabricated parts in subway section
The invention provides a subway section special-shaped prefabricated part mounting method, which comprises the following steps of: arranging door type hoisting equipment above a section to be mounted, combining main hoisting equipment and auxiliary hoisting equipment, and designing a hoisting piece and a rotary hoisting piece on a special-shaped prefabricated part, so that the special-shaped prefabricated part is rotated in a hoisting process; therefore, accurate positioning of components is guaranteed, and construction difficulty is reduced. The construction safety and convenience are improved; the method is particularly suitable for special-shaped prefabricated parts, and can effectively solve the problems that in the prior art, due to the fact that adjustment operation of installation directions such as rotation cannot be achieved in the hoisting process of the prefabricated parts, accurate positioning of the parts is difficult to guarantee, the construction period is long, and construction is difficult.
本发明提供一种地铁区间异型预制构件安装方法,通过在待安装区间的上方设置门式起吊设备,主吊装设备和辅助吊装设备相结合,以及异型预制构件上的吊件及旋转吊件的设计使异型预制构件在吊装过程中实现转体,从而保证构件准确定位,降低施工难度;提高了施工安全性及便捷性;特别适合异型预制构件,本发明能够有效解决现有技术中存在的预制构件在吊装过程中无法实现转体等安装方位的调整作业,导致难以保证构件准确定位,存在施工工期长、施工困难等问题。
Method for installing special-shaped prefabricated parts in subway section
The invention provides a subway section special-shaped prefabricated part mounting method, which comprises the following steps of: arranging door type hoisting equipment above a section to be mounted, combining main hoisting equipment and auxiliary hoisting equipment, and designing a hoisting piece and a rotary hoisting piece on a special-shaped prefabricated part, so that the special-shaped prefabricated part is rotated in a hoisting process; therefore, accurate positioning of components is guaranteed, and construction difficulty is reduced. The construction safety and convenience are improved; the method is particularly suitable for special-shaped prefabricated parts, and can effectively solve the problems that in the prior art, due to the fact that adjustment operation of installation directions such as rotation cannot be achieved in the hoisting process of the prefabricated parts, accurate positioning of the parts is difficult to guarantee, the construction period is long, and construction is difficult.
本发明提供一种地铁区间异型预制构件安装方法,通过在待安装区间的上方设置门式起吊设备,主吊装设备和辅助吊装设备相结合,以及异型预制构件上的吊件及旋转吊件的设计使异型预制构件在吊装过程中实现转体,从而保证构件准确定位,降低施工难度;提高了施工安全性及便捷性;特别适合异型预制构件,本发明能够有效解决现有技术中存在的预制构件在吊装过程中无法实现转体等安装方位的调整作业,导致难以保证构件准确定位,存在施工工期长、施工困难等问题。
Method for installing special-shaped prefabricated parts in subway section
地铁区间异型预制构件安装方法
14.05.2024
Patent
Elektronische Ressource
Chinesisch
Pouring method for prefabricated parts of fabricated subway station
Europäisches Patentamt | 2023
|Intelligent assembling method for prefabricated parts of assembled subway station
Europäisches Patentamt | 2024
|Construction method for installing and fixing prefabricated parts of building
Europäisches Patentamt | 2020
|Lifting and installing device for arch-shaped prefabricated part
Europäisches Patentamt | 2020
|