The invention discloses a concrete layered pouring method which comprises the following steps: for a to-be-constructed reinforced concrete structure, arranging reinforcing steel bars and installing a concrete pouring template, and forming a concrete pouring cavity with at least one to-be-layered section in the concrete pouring template; a first concrete layering device is inserted into the at least one section to be layered in the first direction through a first concrete layering device inserting groove reserved in the concrete pouring formwork and is matched with the steel bars; a second concrete layering device is inserted into the at least one section to be layered in the second direction through a second concrete layering device inserting groove reserved in the concrete pouring formwork and is matched with the steel bars; and concrete is poured into a cavity, located on one side of the to-be-layered section, in the concrete pouring cavity, and the first concrete layering device and the second concrete layering device are taken out after initial setting and before final setting of the concrete.
本发明公开了一种混凝土分层浇筑方法,包括:针对待施工的钢筋混凝土结构,进行钢筋的布设并安装混凝土浇筑模板,所述混凝土浇筑模板中形成具有至少一个待分层截面的混凝土浇筑型腔;通过所述混凝土浇筑模板上预留的混凝土分层装置第一插槽,将第一混凝土分层装置沿第一方向插入所述至少一个待分层截面上并与所述钢筋相适配;通过所述混凝土浇筑模板上预留的混凝土分层装置第二插槽,将第二混凝土分层装置沿第二方向插入所述至少一个待分层截面上并与所述钢筋相适配;对所述混凝土浇筑型腔中位于所述至少一个待分层截面一侧的腔体中浇筑混凝土,并在混凝土初凝后、终凝前,将所述第一混凝土分层装置和所述第二混凝土分层装置取出。
Concrete layered pouring method
The invention discloses a concrete layered pouring method which comprises the following steps: for a to-be-constructed reinforced concrete structure, arranging reinforcing steel bars and installing a concrete pouring template, and forming a concrete pouring cavity with at least one to-be-layered section in the concrete pouring template; a first concrete layering device is inserted into the at least one section to be layered in the first direction through a first concrete layering device inserting groove reserved in the concrete pouring formwork and is matched with the steel bars; a second concrete layering device is inserted into the at least one section to be layered in the second direction through a second concrete layering device inserting groove reserved in the concrete pouring formwork and is matched with the steel bars; and concrete is poured into a cavity, located on one side of the to-be-layered section, in the concrete pouring cavity, and the first concrete layering device and the second concrete layering device are taken out after initial setting and before final setting of the concrete.
本发明公开了一种混凝土分层浇筑方法,包括:针对待施工的钢筋混凝土结构,进行钢筋的布设并安装混凝土浇筑模板,所述混凝土浇筑模板中形成具有至少一个待分层截面的混凝土浇筑型腔;通过所述混凝土浇筑模板上预留的混凝土分层装置第一插槽,将第一混凝土分层装置沿第一方向插入所述至少一个待分层截面上并与所述钢筋相适配;通过所述混凝土浇筑模板上预留的混凝土分层装置第二插槽,将第二混凝土分层装置沿第二方向插入所述至少一个待分层截面上并与所述钢筋相适配;对所述混凝土浇筑型腔中位于所述至少一个待分层截面一侧的腔体中浇筑混凝土,并在混凝土初凝后、终凝前,将所述第一混凝土分层装置和所述第二混凝土分层装置取出。
Concrete layered pouring method
一种混凝土分层浇筑方法
YANG ZHONGYUAN (Autor:in) / LIU PING (Autor:in) / ZHOU RENJIE (Autor:in) / LIU GANG (Autor:in) / TIAN ZEHUI (Autor:in) / WU XUEPING (Autor:in)
28.05.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Frame column concrete pouring concrete layered vibrating equipment
Europäisches Patentamt | 2024
|Concrete layered pouring type arch ring construction method
Europäisches Patentamt | 2020
|Concrete pouring formwork and concrete pouring method
Europäisches Patentamt | 2023
|Method for preventing temperature cracks of layered pouring concrete
Europäisches Patentamt | 2023
|