Grouting system for highway bridge construction
The invention discloses a grouting system for highway bridge construction, and relates to the technical field of bridge foundation scouring protection, the grouting system comprises a drill bit, the drill bit is provided with a grouting hole and a plugging mechanism, and the grouting hole is constructed at the bottom of the drill bit; the plugging mechanism has a first state and a second state, in the first state, the plugging mechanism leaks the grouting hole and plugs the drill hole, and in the second state, the plugging mechanism plugs the grouting hole and relieves plugging of the drill hole. According to the grouting system for highway bridge construction, by arranging the plugging mechanism, when the drill bit conducts drilling, the plugging mechanism is in the second state, so that the grouting hole is plugged in the drilling process, the grouting hole is prevented from being plugged as much as possible, after drilling is completed, the plugging mechanism is in the first state, and the plugging mechanism is in the second state; in this way, the drilled hole can be grouted through the grouting hole, and the drilled hole is blocked in the grouting process, so that the grouting pressure is increased.
本发明公开了公路桥梁施工用注浆系统,涉及桥梁基础冲刷防护技术领域,包括钻头,所述钻头上设置有注浆孔和封堵机构,注浆孔构造于所述钻头的底部;封堵机构具有第一状态和第二状态,在所述第一状态,所述封堵机构将注浆孔漏出并对钻孔进行封堵,在所述第二状态,所述封堵机构对注浆孔进行封堵并解除对钻孔的封堵。本发明提供的公路桥梁施工用注浆系统,通过设置封堵机构,在钻头进行钻孔时,封堵机构处于第二状态,以此在钻孔的过程中对注浆孔进行封堵,尽量避免注浆孔被堵塞,在钻孔结束后,使封堵机构处于第一状态,如此可以通过注浆孔对钻孔进行注浆,且在注浆的过程中钻孔受到封堵,以此提高注浆压强。
Grouting system for highway bridge construction
The invention discloses a grouting system for highway bridge construction, and relates to the technical field of bridge foundation scouring protection, the grouting system comprises a drill bit, the drill bit is provided with a grouting hole and a plugging mechanism, and the grouting hole is constructed at the bottom of the drill bit; the plugging mechanism has a first state and a second state, in the first state, the plugging mechanism leaks the grouting hole and plugs the drill hole, and in the second state, the plugging mechanism plugs the grouting hole and relieves plugging of the drill hole. According to the grouting system for highway bridge construction, by arranging the plugging mechanism, when the drill bit conducts drilling, the plugging mechanism is in the second state, so that the grouting hole is plugged in the drilling process, the grouting hole is prevented from being plugged as much as possible, after drilling is completed, the plugging mechanism is in the first state, and the plugging mechanism is in the second state; in this way, the drilled hole can be grouted through the grouting hole, and the drilled hole is blocked in the grouting process, so that the grouting pressure is increased.
本发明公开了公路桥梁施工用注浆系统,涉及桥梁基础冲刷防护技术领域,包括钻头,所述钻头上设置有注浆孔和封堵机构,注浆孔构造于所述钻头的底部;封堵机构具有第一状态和第二状态,在所述第一状态,所述封堵机构将注浆孔漏出并对钻孔进行封堵,在所述第二状态,所述封堵机构对注浆孔进行封堵并解除对钻孔的封堵。本发明提供的公路桥梁施工用注浆系统,通过设置封堵机构,在钻头进行钻孔时,封堵机构处于第二状态,以此在钻孔的过程中对注浆孔进行封堵,尽量避免注浆孔被堵塞,在钻孔结束后,使封堵机构处于第一状态,如此可以通过注浆孔对钻孔进行注浆,且在注浆的过程中钻孔受到封堵,以此提高注浆压强。
Grouting system for highway bridge construction
公路桥梁施工用注浆系统
YIN XIAOXIA (Autor:in) / LYU DANFENG (Autor:in) / WANG XINGXUAN (Autor:in)
14.06.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Grouting device and grouting method for highway bridge construction
Europäisches Patentamt | 2021
|Grouting device and grouting method for highway bridge construction
Europäisches Patentamt | 2024
|Foundation grouting method for highway bridge construction
Europäisches Patentamt | 2024
|