Fixed water supply pump station arrangement method under riverbed water level variable amplitude
The invention discloses a fixed water supply pump station arrangement method under riverbed water level amplitude variation. The method comprises the steps that 1, an annual maximum riverbed water level predicted value is obtained through an LSTM neural network model; 2, pump station platform construction is conducted according to the annual maximum riverbed water level predicted value; 3, hoisting a water pump and a pipeline; 4, mounting a water storage tank; and fifthly, the centrifugal pump works under the riverbed water level variable amplitude. The method is simple in step, reasonable in design, convenient to construct, low in cost, capable of being suitable for riverbed water level amplitude variation, high in adaptability to the surrounding environment, capable of being repeatedly used and low in overall construction and operation cost.
本发明公开了一种河床水位变幅下的固定式供水泵站布置方法,包括:一、采用LSTM神经网络模型得到年最大河床水位预测值;二、根据年最大河床水位预测值进行泵站平台施工;三、水泵及管路吊装;四、蓄水箱安装;五、河床水位变幅下离心泵的工作。本发明方法步骤简单、设计合理,施工便捷,成本低,能适合河床水位变幅,且对周边环境的适应性强,可重复利用,整体施工及运行成本较低。
Fixed water supply pump station arrangement method under riverbed water level variable amplitude
The invention discloses a fixed water supply pump station arrangement method under riverbed water level amplitude variation. The method comprises the steps that 1, an annual maximum riverbed water level predicted value is obtained through an LSTM neural network model; 2, pump station platform construction is conducted according to the annual maximum riverbed water level predicted value; 3, hoisting a water pump and a pipeline; 4, mounting a water storage tank; and fifthly, the centrifugal pump works under the riverbed water level variable amplitude. The method is simple in step, reasonable in design, convenient to construct, low in cost, capable of being suitable for riverbed water level amplitude variation, high in adaptability to the surrounding environment, capable of being repeatedly used and low in overall construction and operation cost.
本发明公开了一种河床水位变幅下的固定式供水泵站布置方法,包括:一、采用LSTM神经网络模型得到年最大河床水位预测值;二、根据年最大河床水位预测值进行泵站平台施工;三、水泵及管路吊装;四、蓄水箱安装;五、河床水位变幅下离心泵的工作。本发明方法步骤简单、设计合理,施工便捷,成本低,能适合河床水位变幅,且对周边环境的适应性强,可重复利用,整体施工及运行成本较低。
Fixed water supply pump station arrangement method under riverbed water level variable amplitude
一种河床水位变幅下的固定式供水泵站布置方法
GAO ZHENGXU (Autor:in) / WU GANG (Autor:in) / JANG YOUNG-JIN (Autor:in) / HUANG WEI (Autor:in) / MA XUN (Autor:in) / CAO YONGHUI (Autor:in) / MAO HAOYANG (Autor:in) / LI MAOSHENG (Autor:in) / FENG MAOJING (Autor:in)
21.06.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E03B
Anlagen oder Verfahren zum Gewinnen, Sammeln oder Verteilen von Wasser
,
INSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
/
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
/
G06N
COMPUTER SYSTEMS BASED ON SPECIFIC COMPUTATIONAL MODELS
,
Rechnersysteme, basierend auf spezifischen Rechenmodellen
Riverbed fixed distribution structure and riverbed fixed analysis method