Fluid soil micropore cast-in-place pile for installing sloping field photovoltaic module and construction method of fluid soil micropore cast-in-place pile
The invention discloses a flow-state soil micropore cast-in-place pile for slope photovoltaic module installation and a construction method thereof.The flow-state soil micropore cast-in-place pile comprises flow-state soil poured into a miniature pile hole, and the flow-state soil comprises in-situ soil and a soil curing agent; the lower end of the reinforcing casing pipe is inserted into the flow-state soil, and the upper end of the reinforcing casing pipe extends to the position above the micro pile hole; the vertical pipe is used for installing a photovoltaic module, the lower end of the vertical pipe is connected with an end sealing plate, and the lower end of the vertical pipe is inserted into the upper end of the reinforcing sleeve and extends to the middle of the reinforcing sleeve; and the multiple empennages are connected to the lower end of the reinforcing sleeve, and the multiple empennages are arranged at intervals in the circumferential direction of the reinforcing sleeve. The problems of long construction period and high cost when a traditional concrete pile foundation is adopted when a photovoltaic project is built on a slope are solved.
本发明公开了一种用于坡地光伏组件安装的流态土微孔灌注桩及其施工方法,包括:流态土,灌注于微型桩孔中,所述流态土包括原地土和土壤固化剂;加固套管,所述加固套管的下端插设于所述流态土中,所述加固套管的上端伸至所述微型桩孔的上方;用于安装光伏组件的立管,所述立管的下端连接有封端板,所述立管的下端插设于所述加固套管的上端中且伸至所述加固套管的中部;多根尾翼,连接于所述加固套管的下端,所述多根尾翼沿所述加固套管的圆周方向间隔设置。本发明解决了在坡地建筑光伏项目时,采用传统的混凝土桩基础时,施工工期长和成本高的问题。
Fluid soil micropore cast-in-place pile for installing sloping field photovoltaic module and construction method of fluid soil micropore cast-in-place pile
The invention discloses a flow-state soil micropore cast-in-place pile for slope photovoltaic module installation and a construction method thereof.The flow-state soil micropore cast-in-place pile comprises flow-state soil poured into a miniature pile hole, and the flow-state soil comprises in-situ soil and a soil curing agent; the lower end of the reinforcing casing pipe is inserted into the flow-state soil, and the upper end of the reinforcing casing pipe extends to the position above the micro pile hole; the vertical pipe is used for installing a photovoltaic module, the lower end of the vertical pipe is connected with an end sealing plate, and the lower end of the vertical pipe is inserted into the upper end of the reinforcing sleeve and extends to the middle of the reinforcing sleeve; and the multiple empennages are connected to the lower end of the reinforcing sleeve, and the multiple empennages are arranged at intervals in the circumferential direction of the reinforcing sleeve. The problems of long construction period and high cost when a traditional concrete pile foundation is adopted when a photovoltaic project is built on a slope are solved.
本发明公开了一种用于坡地光伏组件安装的流态土微孔灌注桩及其施工方法,包括:流态土,灌注于微型桩孔中,所述流态土包括原地土和土壤固化剂;加固套管,所述加固套管的下端插设于所述流态土中,所述加固套管的上端伸至所述微型桩孔的上方;用于安装光伏组件的立管,所述立管的下端连接有封端板,所述立管的下端插设于所述加固套管的上端中且伸至所述加固套管的中部;多根尾翼,连接于所述加固套管的下端,所述多根尾翼沿所述加固套管的圆周方向间隔设置。本发明解决了在坡地建筑光伏项目时,采用传统的混凝土桩基础时,施工工期长和成本高的问题。
Fluid soil micropore cast-in-place pile for installing sloping field photovoltaic module and construction method of fluid soil micropore cast-in-place pile
用于坡地光伏组件安装的流态土微孔灌注桩及其施工方法
WANG ZHIZHUANG (Autor:in) / LI CAN (Autor:in)
12.07.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Gobi desert micropore cast-in-place pile hole and micropore cast-in-place pile construction method
Europäisches Patentamt | 2024
|Photovoltaic power station micropore cast-in-place pile foundation construction device
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2023
|CAST-IN-PLACE PILE AND CONSTRUCTION METHOD OF CAST-IN-PLACE PILE
Europäisches Patentamt | 2023
|Cast-in-place pile casing device, cast-in-place pile and construction method
Europäisches Patentamt | 2024
|