Overall installation and construction process for ultra-long prefabricated square pile
The invention discloses an overall installation and construction technology for an ultra-long prefabricated square pile, and belongs to the technical field of building construction. The overall installation and construction technology comprises the following steps that S1000, a lower pile platform is installed; s2000, the square pile is hoisted; s3000, the square pile is rotated; s4000, the square piles are conveyed; and S5000, the next pile position is constructed. The method is suitable for installation and construction of the ultra-long prefabricated square pile, the hoisting safety problem of the ultra-long prefabricated square pile is solved, the installation time of the prefabricated square pile is shortened, the installation precision of the prefabricated square pile is improved, and a powerful guarantee is provided for installation of the project prefabricated square pile with quality and quantity guaranteed.
本发明公开了一种超长预制方桩整体安装施工工艺,属于建筑施工技术领域,包括以下步骤:S1000、安装好下桩平台;S2000、方桩起吊;S3000、方桩转体;S4000、方桩送桩;S5000、下一桩位施工。本发明可适用于超长预制方桩的安装施工,解决了超长预制方桩的吊装安全问题,降低了预制方桩安装时间,提高了预制方桩的安装精度,为项目预制方桩保质保量的安装提供了有力保障。
Overall installation and construction process for ultra-long prefabricated square pile
The invention discloses an overall installation and construction technology for an ultra-long prefabricated square pile, and belongs to the technical field of building construction. The overall installation and construction technology comprises the following steps that S1000, a lower pile platform is installed; s2000, the square pile is hoisted; s3000, the square pile is rotated; s4000, the square piles are conveyed; and S5000, the next pile position is constructed. The method is suitable for installation and construction of the ultra-long prefabricated square pile, the hoisting safety problem of the ultra-long prefabricated square pile is solved, the installation time of the prefabricated square pile is shortened, the installation precision of the prefabricated square pile is improved, and a powerful guarantee is provided for installation of the project prefabricated square pile with quality and quantity guaranteed.
本发明公开了一种超长预制方桩整体安装施工工艺,属于建筑施工技术领域,包括以下步骤:S1000、安装好下桩平台;S2000、方桩起吊;S3000、方桩转体;S4000、方桩送桩;S5000、下一桩位施工。本发明可适用于超长预制方桩的安装施工,解决了超长预制方桩的吊装安全问题,降低了预制方桩安装时间,提高了预制方桩的安装精度,为项目预制方桩保质保量的安装提供了有力保障。
Overall installation and construction process for ultra-long prefabricated square pile
一种超长预制方桩整体安装施工工艺
YI LINGBING (Autor:in) / ZHANG LEI (Autor:in) / NING JICHAO (Autor:in) / LI XIN (Autor:in) / LI WEIZHOU (Autor:in) / LIU BOFENG (Autor:in) / CHEN QINGHUAI (Autor:in) / ZHANG MINGXU (Autor:in) / ZHENG LIMING (Autor:in) / SHAO QI (Autor:in)
16.07.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Prefabricated square pile and construction process thereof
Europäisches Patentamt | 2021
|Prefabricated pile installation construction guide frame
Europäisches Patentamt | 2023
|Prefabricated small square pile construction positioning equipment
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2016
|Prefabricated pipe pile for construction of ultra-long stiff composite pile and construction method
Europäisches Patentamt | 2020
|