Support-free active closing construction method for large-span steel box girder
The invention relates to the technical field of installation and construction of steel box girders, and provides a non-support active closure construction method for a large-span steel box girder, which comprises the following steps: S1, constructing the top of a pier to the design elevation of a low pier structure; s2, a falling support is constructed at the position of a low pier structure of the pier; s3, an adjusting mechanism is installed at the low pier structure of the pier; and S4, hoisting equipment is installed at the end of the steel-concrete combined section. S5, the bottom side of one end of the steel box girder abuts against the temporary support through a floating crane, and the other end of the steel box girder is hoisted through hoisting equipment; s6, the floating crane and the steel box girder are disconnected; s7, adjusting the position of the steel box girder; s8, dismantling the temporary support; s9, the steel box girder is lowered through cooperation of the jacking jack and the hoisting equipment until the bottom of the steel box girder abuts against the falling support; s10, welding and fixing the closure end of the steel box girder and the end part of the steel-concrete combined section; and S11, a high pier structure of the pier is constructed. The method has the effect of facilitating installation and construction of the steel box girder.
本申请涉及钢箱梁安装施工的技术领域,提出了一种大跨径钢箱梁的无支架主动合拢施工方法,包括以下步骤:S1:桥墩顶部施工至低墩结构设计标高;S2:在桥墩的低墩结构处施工落位支座;S3:在桥墩的低墩结构处安装调节机构,S4:在钢混结合段端部安装吊装设备。S5:通过浮吊使钢箱梁一端底侧与临时支座抵接,将钢箱梁的另一端通过吊接设备吊起;S6:断开浮吊与钢箱梁的连接;S7:钢箱梁位置调节;S8:拆除临时支座;S9:通过顶升千斤顶配合吊装设备下放钢箱梁,直至钢箱梁底部抵接于落位支座;S10:将钢箱梁合拢端与钢混结合段端部进行焊接固定;S11:施作桥墩的高墩结构。本申请具有便于钢箱梁安装施工的效果。
Support-free active closing construction method for large-span steel box girder
The invention relates to the technical field of installation and construction of steel box girders, and provides a non-support active closure construction method for a large-span steel box girder, which comprises the following steps: S1, constructing the top of a pier to the design elevation of a low pier structure; s2, a falling support is constructed at the position of a low pier structure of the pier; s3, an adjusting mechanism is installed at the low pier structure of the pier; and S4, hoisting equipment is installed at the end of the steel-concrete combined section. S5, the bottom side of one end of the steel box girder abuts against the temporary support through a floating crane, and the other end of the steel box girder is hoisted through hoisting equipment; s6, the floating crane and the steel box girder are disconnected; s7, adjusting the position of the steel box girder; s8, dismantling the temporary support; s9, the steel box girder is lowered through cooperation of the jacking jack and the hoisting equipment until the bottom of the steel box girder abuts against the falling support; s10, welding and fixing the closure end of the steel box girder and the end part of the steel-concrete combined section; and S11, a high pier structure of the pier is constructed. The method has the effect of facilitating installation and construction of the steel box girder.
本申请涉及钢箱梁安装施工的技术领域,提出了一种大跨径钢箱梁的无支架主动合拢施工方法,包括以下步骤:S1:桥墩顶部施工至低墩结构设计标高;S2:在桥墩的低墩结构处施工落位支座;S3:在桥墩的低墩结构处安装调节机构,S4:在钢混结合段端部安装吊装设备。S5:通过浮吊使钢箱梁一端底侧与临时支座抵接,将钢箱梁的另一端通过吊接设备吊起;S6:断开浮吊与钢箱梁的连接;S7:钢箱梁位置调节;S8:拆除临时支座;S9:通过顶升千斤顶配合吊装设备下放钢箱梁,直至钢箱梁底部抵接于落位支座;S10:将钢箱梁合拢端与钢混结合段端部进行焊接固定;S11:施作桥墩的高墩结构。本申请具有便于钢箱梁安装施工的效果。
Support-free active closing construction method for large-span steel box girder
一种大跨径钢箱梁的无支架主动合拢施工方法
WANG JIE (Autor:in) / ZHENG ZHEN (Autor:in) / LIAO YUNZHAO (Autor:in) / ZHANG FENG (Autor:in) / LAN QIAOXIN (Autor:in) / XIAO JINGTAO (Autor:in)
23.07.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Europäisches Patentamt | 2022
|Large-span steel truss girder single-cantilever construction method
Europäisches Patentamt | 2020
|Large-span curve steel truss girder construction system and construction method
Europäisches Patentamt | 2022
|