Construction method of waterproof joint of basement bottom plate and outer wall
The invention provides a construction method for a waterproof joint of a basement bottom plate and an outer wall, and belongs to the technical field of building construction. S2, a macromolecule self-adhesion waterproof coiled material is pre-laid on the bearing platform beam part; s3, performing throwing and rubbing treatment; and S4, outer wall waterproof roll construction is conducted, and after guide wall concrete pouring is completed and the design strength is achieved, outer wall waterproof roll laying is conducted. According to the scheme, in the waterproof construction process of the bottom plate, 200-300 mm stubbles are thrown to the brick moulding bed, a waterproof layer at the position of the guide wall is temporarily not manufactured when the bottom plate and the guide wall are poured, one piece of stubbles is treated during waterproof construction of the outer wall, and damage of split bolts and outer wall steel bars to waterproof coiled materials is avoided from the source.
本发明提供的一种地下室底板与外墙的防水节点的施工方法,属于建筑施工技术领域,包括步骤:S1、基面处理;S2、承台梁部分预铺高分子自粘防水卷材;S3、甩搓处理;S4、外墙防水卷材施工,待导墙混凝土浇筑完成并达到设计强度后,进行外墙防水卷材的铺设。本方案中在底板防水施工过程中甩茬200‑300mm至砖胎模,浇筑底板及导墙时导墙部位防水层暂不做,待外墙防水施工时一块处理,本发明从源头上避免了对拉螺栓以及外墙钢筋对防水卷材的破坏。
Construction method of waterproof joint of basement bottom plate and outer wall
The invention provides a construction method for a waterproof joint of a basement bottom plate and an outer wall, and belongs to the technical field of building construction. S2, a macromolecule self-adhesion waterproof coiled material is pre-laid on the bearing platform beam part; s3, performing throwing and rubbing treatment; and S4, outer wall waterproof roll construction is conducted, and after guide wall concrete pouring is completed and the design strength is achieved, outer wall waterproof roll laying is conducted. According to the scheme, in the waterproof construction process of the bottom plate, 200-300 mm stubbles are thrown to the brick moulding bed, a waterproof layer at the position of the guide wall is temporarily not manufactured when the bottom plate and the guide wall are poured, one piece of stubbles is treated during waterproof construction of the outer wall, and damage of split bolts and outer wall steel bars to waterproof coiled materials is avoided from the source.
本发明提供的一种地下室底板与外墙的防水节点的施工方法,属于建筑施工技术领域,包括步骤:S1、基面处理;S2、承台梁部分预铺高分子自粘防水卷材;S3、甩搓处理;S4、外墙防水卷材施工,待导墙混凝土浇筑完成并达到设计强度后,进行外墙防水卷材的铺设。本方案中在底板防水施工过程中甩茬200‑300mm至砖胎模,浇筑底板及导墙时导墙部位防水层暂不做,待外墙防水施工时一块处理,本发明从源头上避免了对拉螺栓以及外墙钢筋对防水卷材的破坏。
Construction method of waterproof joint of basement bottom plate and outer wall
一种地下室底板与外墙的防水节点的施工方法
LI YUNJIE (Autor:in) / SHEN YINPING (Autor:in) / YANG SIJIE (Autor:in) / LI LONGFEI (Autor:in) / ZHANG WEI (Autor:in) / WANG ZELIN (Autor:in) / CUI HUAN (Autor:in) / ZHANG SHIMENG (Autor:in) / DU WEI (Autor:in) / REN JINGLEI (Autor:in)
23.08.2024
Patent
Elektronische Ressource
Chinesisch
Construction method of basement bottom plate and outer wall waterproof structure
Europäisches Patentamt | 2022
|Basement bottom plate and outer wall waterproof structure and construction method thereof
Europäisches Patentamt | 2021
|High-rise basement bottom plate and outer wall waterproof structure and construction method
Europäisches Patentamt | 2024
|Basement outer wall construction joint waterproof structure and construction method
Europäisches Patentamt | 2024
|Waterproof construction method for basement outer wall
Europäisches Patentamt | 2023
|