Construction device and construction method for improving filling precision of underwater filling pile
The invention discloses a construction device and method for improving the filling precision of an underwater filling pile, and relates to the technical field of filling pile construction, the construction device comprises a workbench which is placed on a to-be-filled hole site, the workbench is provided with a filling space, and the filling space communicates with the to-be-filled hole site and allows a guide pipe to pass through the workbench; the catheter clamping assembly is located above the workbench, and the catheter clamping assembly is used for clamping a catheter to the perfusion space; the gravity clamping assembly is close to the filling space and is arranged on the workbench; when the catheter passes through the perfusion space, the gravity clamping assembly can be adsorbed to the end, close to a to-be-perfused hole, of the catheter. By the adoption of the technical scheme, it is ensured that the guide pipe is kept vertical and stable in the pouring process, the guide pipe is prevented from inclining, and the pouring precision of the underwater pouring pile is remarkably improved.
本申请公开了一种提高水下灌注桩灌注精度的施工装置及施工方法,涉及灌注桩施工技术领域,包括工作台,放置在待灌注孔位上,所述工作台具有灌注空间,所述灌注空间与待灌注孔位相互连通且供导管通过所述工作台;导管夹持组件,位于所述工作台的上方,所述导管夹持组件用于夹持导管到所述灌注空间上;重力加持组件,靠近所述灌注空间设置在所述工作台上;其中当导管经过所述灌注空间时,所述重力加持组件能够吸附到导管靠近待灌注孔位的一端。通过采用上述技术方案,确保了导管在灌注过程中保持垂直和稳定,避免了导管倾斜,显著提高了水下灌注桩的灌注精度。
Construction device and construction method for improving filling precision of underwater filling pile
The invention discloses a construction device and method for improving the filling precision of an underwater filling pile, and relates to the technical field of filling pile construction, the construction device comprises a workbench which is placed on a to-be-filled hole site, the workbench is provided with a filling space, and the filling space communicates with the to-be-filled hole site and allows a guide pipe to pass through the workbench; the catheter clamping assembly is located above the workbench, and the catheter clamping assembly is used for clamping a catheter to the perfusion space; the gravity clamping assembly is close to the filling space and is arranged on the workbench; when the catheter passes through the perfusion space, the gravity clamping assembly can be adsorbed to the end, close to a to-be-perfused hole, of the catheter. By the adoption of the technical scheme, it is ensured that the guide pipe is kept vertical and stable in the pouring process, the guide pipe is prevented from inclining, and the pouring precision of the underwater pouring pile is remarkably improved.
本申请公开了一种提高水下灌注桩灌注精度的施工装置及施工方法,涉及灌注桩施工技术领域,包括工作台,放置在待灌注孔位上,所述工作台具有灌注空间,所述灌注空间与待灌注孔位相互连通且供导管通过所述工作台;导管夹持组件,位于所述工作台的上方,所述导管夹持组件用于夹持导管到所述灌注空间上;重力加持组件,靠近所述灌注空间设置在所述工作台上;其中当导管经过所述灌注空间时,所述重力加持组件能够吸附到导管靠近待灌注孔位的一端。通过采用上述技术方案,确保了导管在灌注过程中保持垂直和稳定,避免了导管倾斜,显著提高了水下灌注桩的灌注精度。
Construction device and construction method for improving filling precision of underwater filling pile
一种提高水下灌注桩灌注精度的施工装置及施工方法
WANG ZHIGUO (Autor:in) / WANG XIAOSHUAI (Autor:in) / MA XIAOLIANG (Autor:in) / ZHANG CHANGJIE (Autor:in) / LIU WENHAO (Autor:in)
27.09.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen