Aluminum mold mounting method for high-rise fabricated building
The invention discloses an aluminum mold mounting method for a high-rise fabricated building. The aluminum mold mounting method comprises the steps that aluminum mold partitions are divided; deepening aluminum mold mounting nodes and drawing an aluminum mold mounting drawing; preparing an aluminum mold and accessories; pre-burying reinforcing steel bars; mounting aluminum molds of the wall columns, the beams and the plates; hoisting the assembly type laminated slab; the construction method comprises eight steps of concrete pouring and maintenance, column aluminum formwork dismantling and beam and plate aluminum formwork dismantling, aluminum formworks are numbered according to areas and stacked according to the areas, and the construction efficiency of installation and dismantling is improved; on the other hand, due to the fact that the rigidity of the aluminum mold is better than that of the wood mold, the attaching effect of the aluminum mold and the assembly type laminated plate is better, and deformation and slurry leakage of the assembly type laminated plate during concrete pouring can be effectively reduced; the water and electricity pre-embedded wire duct and the fire box are pre-embedded and formed at one time, the forming quality is good, and the position is accurate; constructional columns, special-shaped columns and lintels of secondary structure door edges and brick walls and a main body structure are subjected to formwork erection, concrete pouring and one-time forming together, a series of tedious working procedures such as steel bar planting, formwork erection, concrete pouring and plastering of the constructional columns and the special-shaped columns during secondary structure construction are omitted, the working procedures are simplified, the construction cost is saved, and the construction quality is guaranteed.
本发明公开了一种高层装配式建筑的铝模安装方法,包括:划分铝模分区;深化铝模安装节点及绘制铝模安装图;准备铝模及配件;预埋加固钢筋;安装墙柱、梁和板的铝模;装配式叠合板吊装;混凝土浇筑及养护和柱铝模拆除及梁、板铝模拆除8个步骤,铝模按区域编号,按区域进行堆放,提高了安装拆除的施工效率;另一方面,由于铝模的刚度好于木模,铝模和装配式叠合板的贴合效果更好,能够有效地减少浇筑混凝土时装配式叠合板发生变形及漏浆;水电预埋线槽及消防箱预埋一次成型,成型质量好,位置精确;二次结构门边及砖墙的构造柱、异形柱、过梁与主体结构一起支模安装浇筑混凝土,一次成型,省去二次结构施工时构造柱及异形柱植筋、支模、浇筑混凝土、抹灰等一系列繁琐工序,简化工序,节约施工成本,保证施工质量。
Aluminum mold mounting method for high-rise fabricated building
The invention discloses an aluminum mold mounting method for a high-rise fabricated building. The aluminum mold mounting method comprises the steps that aluminum mold partitions are divided; deepening aluminum mold mounting nodes and drawing an aluminum mold mounting drawing; preparing an aluminum mold and accessories; pre-burying reinforcing steel bars; mounting aluminum molds of the wall columns, the beams and the plates; hoisting the assembly type laminated slab; the construction method comprises eight steps of concrete pouring and maintenance, column aluminum formwork dismantling and beam and plate aluminum formwork dismantling, aluminum formworks are numbered according to areas and stacked according to the areas, and the construction efficiency of installation and dismantling is improved; on the other hand, due to the fact that the rigidity of the aluminum mold is better than that of the wood mold, the attaching effect of the aluminum mold and the assembly type laminated plate is better, and deformation and slurry leakage of the assembly type laminated plate during concrete pouring can be effectively reduced; the water and electricity pre-embedded wire duct and the fire box are pre-embedded and formed at one time, the forming quality is good, and the position is accurate; constructional columns, special-shaped columns and lintels of secondary structure door edges and brick walls and a main body structure are subjected to formwork erection, concrete pouring and one-time forming together, a series of tedious working procedures such as steel bar planting, formwork erection, concrete pouring and plastering of the constructional columns and the special-shaped columns during secondary structure construction are omitted, the working procedures are simplified, the construction cost is saved, and the construction quality is guaranteed.
本发明公开了一种高层装配式建筑的铝模安装方法,包括:划分铝模分区;深化铝模安装节点及绘制铝模安装图;准备铝模及配件;预埋加固钢筋;安装墙柱、梁和板的铝模;装配式叠合板吊装;混凝土浇筑及养护和柱铝模拆除及梁、板铝模拆除8个步骤,铝模按区域编号,按区域进行堆放,提高了安装拆除的施工效率;另一方面,由于铝模的刚度好于木模,铝模和装配式叠合板的贴合效果更好,能够有效地减少浇筑混凝土时装配式叠合板发生变形及漏浆;水电预埋线槽及消防箱预埋一次成型,成型质量好,位置精确;二次结构门边及砖墙的构造柱、异形柱、过梁与主体结构一起支模安装浇筑混凝土,一次成型,省去二次结构施工时构造柱及异形柱植筋、支模、浇筑混凝土、抹灰等一系列繁琐工序,简化工序,节约施工成本,保证施工质量。
Aluminum mold mounting method for high-rise fabricated building
一种高层装配式建筑的铝模安装方法
LIANG XU (Autor:in) / HUANG JIANGYU (Autor:in) / LIN QIANG (Autor:in) / ZHAO JUHUI (Autor:in) / CHEN WEIPENG (Autor:in) / LIU HAO (Autor:in) / HUANG XIAOLI (Autor:in) / LIANG XIANGLONG (Autor:in)
01.10.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Europäisches Patentamt | 2024
|Aluminum mold for fabricated building and using method of aluminum mold
Europäisches Patentamt | 2022
|Fabricated aluminum alloy building template and mounting process
Europäisches Patentamt | 2023
|High-rise building bay window aluminum alloy formwork mounting and reinforcing method
Europäisches Patentamt | 2022
|Aluminum mold lifting and mounting robot and aluminum mold lifting and mounting method applying same
Europäisches Patentamt | 2021
|