Installation method of high-altitude TBM rockburst tunnel formwork trolley
The invention relates to the technical field of installation of tunnel lining construction equipment, in particular to an installation method of a high-altitude TBM rockburst tunnel formwork trolley, which comprises the following assembly steps: laying a temporary track, splicing a main body structure, installing a material distribution system, hoisting by a gantry crane, and installing a belt conveyor and a formwork, and a transport vehicle channel is reserved. The problems that when the trolley is installed in the high-altitude TBM tunnel hole, deslagging of a belt conveyor is affected, transportation vehicles pass, air stopping, water stopping, power failure and the like are solved, and the construction progress is effectively guaranteed.
本发明涉及隧道衬砌施工设备安装技术领域,特别是一种高海拔TBM岩爆隧道模板台车的安装方法,包括以下组装步骤:临时轨道铺设、主体结构拼装、布料系统安装、龙门吊吊运、皮带机和模板安装,所述临时轨道铺设在组装洞的左侧位置,并预留运输车通道。本发明解决了高海拔TBM隧道洞内安装台车时皮带机出渣受影响、运输车辆通行、停风停水停电等问题,有效保障了施工进度。
Installation method of high-altitude TBM rockburst tunnel formwork trolley
The invention relates to the technical field of installation of tunnel lining construction equipment, in particular to an installation method of a high-altitude TBM rockburst tunnel formwork trolley, which comprises the following assembly steps: laying a temporary track, splicing a main body structure, installing a material distribution system, hoisting by a gantry crane, and installing a belt conveyor and a formwork, and a transport vehicle channel is reserved. The problems that when the trolley is installed in the high-altitude TBM tunnel hole, deslagging of a belt conveyor is affected, transportation vehicles pass, air stopping, water stopping, power failure and the like are solved, and the construction progress is effectively guaranteed.
本发明涉及隧道衬砌施工设备安装技术领域,特别是一种高海拔TBM岩爆隧道模板台车的安装方法,包括以下组装步骤:临时轨道铺设、主体结构拼装、布料系统安装、龙门吊吊运、皮带机和模板安装,所述临时轨道铺设在组装洞的左侧位置,并预留运输车通道。本发明解决了高海拔TBM隧道洞内安装台车时皮带机出渣受影响、运输车辆通行、停风停水停电等问题,有效保障了施工进度。
Installation method of high-altitude TBM rockburst tunnel formwork trolley
一种高海拔TBM岩爆隧道模板台车的安装方法
LI ZHIJUN (Autor:in) / CHEN WENYI (Autor:in) / LYU JIANLE (Autor:in) / YANG ZHI (Autor:in) / WU YI (Autor:in) / WANG YANBO (Autor:in) / MA XIAOBING (Autor:in) / WANG BIAO (Autor:in) / ZHANG LEFENG (Autor:in) / HUANG QINGHUA (Autor:in)
01.10.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E21D
SHAFTS
,
Schächte
/
E01B
PERMANENT WAY
,
Gleisoberbau
/
E21F
Sicherheitsvorrichtungen, Förderung, Auffüllen oder Bergversatz, Rettungswesen, Bewetterung oder Entwässerung in oder von Gruben oder Tunnels
,
SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINAGE IN OR OF MINES OR TUNNELS
/
F16L
PIPES
,
Rohre
/
H02G
INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
,
Verlegen oder Installieren elektrischer Kabel oder Leitungen, Verlegen oder Installieren kombinierter optischer und elektrischer Kabel oder Leitungen
Lining formwork trolley for open-cut rectangular tunnel
Europäisches Patentamt | 2021
|Efficient lining TBM rock burst tunnel formwork trolley
Europäisches Patentamt | 2024
|Formwork trolley of top longitudinal beam and construction method of formwork trolley
Europäisches Patentamt | 2024
|