Concrete-filled steel tube arch bridge skewback large-angle inclined pile guide arch pouring device and construction method
The invention relates to the field of bridge construction, in particular to a concrete-filled steel tube arch bridge skewback large-angle batter pile arch guide pouring device and a construction method.The concrete-filled steel tube arch bridge skewback large-angle batter pile arch guide pouring device comprises a rock groove, an arch guide foundation and a set-shaped steel formwork, the rock groove is formed in a rock wall, and the arch guide foundation is arranged at the bottom of the rock groove; the set-shaped steel formwork is arranged at a groove opening of the rock groove, an anchor rod is arranged between the set-shaped steel formwork and the side wall of the rock groove, one end of the anchor rod is fixedly connected with the side wall of the rock groove, the other end of the anchor rod is fixedly connected with the set-shaped steel formwork, and an attached vibrator is arranged on the set-shaped steel formwork and used for vibrating concrete poured in the set-shaped steel formwork. A pouring opening is formed in the arch-shaped bottom of the set-shaped steel formwork, a slurry outlet is formed in the arch-shaped top of the set-shaped steel formwork, the pouring opening is used for pouring concrete into the rock groove, the slurry outlet is used for discharging laitance in the rock groove, and the effect of accelerating the construction progress of the inclined pile guide arch is achieved.
本申请涉及桥梁施工领域,尤其是涉及一种钢管混凝土拱桥拱座大角度斜桩导拱浇筑装置及施工方法,该钢管混凝土拱桥拱座大角度斜桩导拱浇筑装置包括岩槽、导拱基础和定型钢模板,岩槽开设在岩壁上,导拱基础设置在岩槽底部,定型钢模板设置在岩槽的槽口处,定型钢模板与岩槽的侧壁之间设置有锚杆,锚杆的一端与岩槽的侧壁固定连接,另一端与定型钢模板固定连接,定型钢模板上设置有附着式振捣器,附着式振捣器用于震动定型钢模板内浇筑的混凝土,定型钢模板在拱形的底部设置灌注口,定型钢模板在拱形的顶部设置有出浆口,灌注口用于向岩槽内灌注混凝土,出浆口用于排出岩槽内的浮浆,达到了加快斜桩导拱的施工进度的效果。
Concrete-filled steel tube arch bridge skewback large-angle inclined pile guide arch pouring device and construction method
The invention relates to the field of bridge construction, in particular to a concrete-filled steel tube arch bridge skewback large-angle batter pile arch guide pouring device and a construction method.The concrete-filled steel tube arch bridge skewback large-angle batter pile arch guide pouring device comprises a rock groove, an arch guide foundation and a set-shaped steel formwork, the rock groove is formed in a rock wall, and the arch guide foundation is arranged at the bottom of the rock groove; the set-shaped steel formwork is arranged at a groove opening of the rock groove, an anchor rod is arranged between the set-shaped steel formwork and the side wall of the rock groove, one end of the anchor rod is fixedly connected with the side wall of the rock groove, the other end of the anchor rod is fixedly connected with the set-shaped steel formwork, and an attached vibrator is arranged on the set-shaped steel formwork and used for vibrating concrete poured in the set-shaped steel formwork. A pouring opening is formed in the arch-shaped bottom of the set-shaped steel formwork, a slurry outlet is formed in the arch-shaped top of the set-shaped steel formwork, the pouring opening is used for pouring concrete into the rock groove, the slurry outlet is used for discharging laitance in the rock groove, and the effect of accelerating the construction progress of the inclined pile guide arch is achieved.
本申请涉及桥梁施工领域,尤其是涉及一种钢管混凝土拱桥拱座大角度斜桩导拱浇筑装置及施工方法,该钢管混凝土拱桥拱座大角度斜桩导拱浇筑装置包括岩槽、导拱基础和定型钢模板,岩槽开设在岩壁上,导拱基础设置在岩槽底部,定型钢模板设置在岩槽的槽口处,定型钢模板与岩槽的侧壁之间设置有锚杆,锚杆的一端与岩槽的侧壁固定连接,另一端与定型钢模板固定连接,定型钢模板上设置有附着式振捣器,附着式振捣器用于震动定型钢模板内浇筑的混凝土,定型钢模板在拱形的底部设置灌注口,定型钢模板在拱形的顶部设置有出浆口,灌注口用于向岩槽内灌注混凝土,出浆口用于排出岩槽内的浮浆,达到了加快斜桩导拱的施工进度的效果。
Concrete-filled steel tube arch bridge skewback large-angle inclined pile guide arch pouring device and construction method
钢管混凝土拱桥拱座大角度斜桩导拱浇筑装置及施工方法
KANG YAFEI (Autor:in) / WANG HUAIJIAN (Autor:in) / WANG JINGYU (Autor:in) / YANG HAO (Autor:in) / YAN MINGBO (Autor:in) / LONG XUE (Autor:in) / XIE PENG (Autor:in) / ZHANG CHI (Autor:in) / LIU BAOMIN (Autor:in)
29.10.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Concrete lifting pouring construction method for steel tube arch bridge arch ribs
Europäisches Patentamt | 2015
|Europäisches Patentamt | 2023
|Concrete arch bridge inclined pile construction technology
Europäisches Patentamt | 2024
|Concrete-filled steel tube arch rib, pouring equipment and pouring method
Europäisches Patentamt | 2022
|Arch bridge abutment tunnel type large-angle inclined pile construction method
Europäisches Patentamt | 2015
|