Method for backfilling artificial island in sea area
The invention relates to a sea area artificial island back-filling island-filling method which comprises the following steps: an existing building enclosure is constructed around an existing building to form an enclosure structure, so that the existing building is located in the enclosure structure; the interior of the enclosure structure is backfilled in a layered mode to the top elevation of the enclosure structure, and the backfilling height of each layer is 0.5-1 m; the backfill height of each layer is 0.5-1m, after the backfill height of the sand quilt is 1-2.5 m, a drainage plate is inserted and hit, and then the backfill height is performed in a layered manner, so that it is guaranteed that the existing building is not prone to deviation or inclination in the backfill process, potential safety hazards caused to the existing building in the backfill island filling process are reduced, and the construction safety of the existing building is improved. And the efficiency of backfilling the island is improved.
本发明涉及一种海域人工岛回填筑岛的方法,包括以下步骤:既有建筑围护,围绕既有建筑施工形成围护结构,使得既有建筑位于围护结构内;围护结构内回填,分层回填至围护结构顶部标高,每层回填高度为0.5‑1米;围护结构外回填,底层铺设沙被,在沙被上分层回填,每层回填高度为0.5‑1米,在沙被上回填到1‑2.5米后插打排水板,之后分层回填至设计高度,保证既有建筑在回填中不易出现偏移或倾斜,降低回填筑岛过程中对既有建筑造成的安全隐患,提高了回填筑岛的效率。
Method for backfilling artificial island in sea area
The invention relates to a sea area artificial island back-filling island-filling method which comprises the following steps: an existing building enclosure is constructed around an existing building to form an enclosure structure, so that the existing building is located in the enclosure structure; the interior of the enclosure structure is backfilled in a layered mode to the top elevation of the enclosure structure, and the backfilling height of each layer is 0.5-1 m; the backfill height of each layer is 0.5-1m, after the backfill height of the sand quilt is 1-2.5 m, a drainage plate is inserted and hit, and then the backfill height is performed in a layered manner, so that it is guaranteed that the existing building is not prone to deviation or inclination in the backfill process, potential safety hazards caused to the existing building in the backfill island filling process are reduced, and the construction safety of the existing building is improved. And the efficiency of backfilling the island is improved.
本发明涉及一种海域人工岛回填筑岛的方法,包括以下步骤:既有建筑围护,围绕既有建筑施工形成围护结构,使得既有建筑位于围护结构内;围护结构内回填,分层回填至围护结构顶部标高,每层回填高度为0.5‑1米;围护结构外回填,底层铺设沙被,在沙被上分层回填,每层回填高度为0.5‑1米,在沙被上回填到1‑2.5米后插打排水板,之后分层回填至设计高度,保证既有建筑在回填中不易出现偏移或倾斜,降低回填筑岛过程中对既有建筑造成的安全隐患,提高了回填筑岛的效率。
Method for backfilling artificial island in sea area
海域人工岛回填筑岛的方法
LIU KUN (Autor:in) / PEI CHAO (Autor:in) / HOU YUCHEN (Autor:in) / WAN JIANPING (Autor:in) / ZHU ALONG (Autor:in) / LIU YANPING (Autor:in) / LUO FENGQUAN (Autor:in) / YU JIANJUN (Autor:in) / HE JUN (Autor:in) / CHEN KUN (Autor:in)
29.10.2024
Patent
Elektronische Ressource
Chinesisch
Sea area artificial island backfilling island and undercrossing tunnel excavation method
Europäisches Patentamt | 2024
|Deep water area cofferdam backfilling device and backfilling construction method thereof
Europäisches Patentamt | 2024
|Device and method for backfilling flow-state solidified soil in narrow and high backfilling area
Europäisches Patentamt | 2022
|Sandstone backfilling system and sandstone backfilling method thereof