Construction method for double-sided laminated shear wall of transformer substation
According to the construction method for the double-sided laminated shear wall of the transformer substation, an outer wall positioning line of the double-sided laminated shear wall of the transformer substation is paid off according to the axis relation on a construction drawing of the double-sided laminated shear wall of the transformer substation, and meanwhile, an outer wall installation control line of the double-sided laminated shear wall of the transformer substation is paid off to ensure the accuracy of outer wall installation; a hoisting beam is adopted for hoisting the wallboard of the power station double-sided laminated shear wall, a reasonable hoisting point is arranged according to the position of a hoisting ring of the prefabricated wallboard, after a steel wire rope and a reserved hoisting ring of an outer wallboard are connected through a shackle, the wallboard is hoisted to the position 500 mm away from the ground, and hoisting continues after the appearance quality of a component and the correct connection of the hoisting ring are checked. Before hoisting, the full-length multi-layer board with the width of 500 mm is nailed on the lower side of the prefabricated wallboard to be hoisted at a constant speed, so that it is ensured that the edge of the prefabricated wallboard is not damaged, and the defects that the installation accuracy of the outer wall of the double-sided laminated shear wall of the transformer substation is insufficient and the edge of the prefabricated wallboard of the double-sided laminated shear wall of the transformer substation is prone to being damaged are effectively overcome.
一种针对变电站双面叠合剪力墙的施工方法,根据变电站双面叠合剪力墙的施工图纸上的轴线关系放出变电站双面叠合剪力墙的外墙定位线,同时放出变电站双面叠合剪力墙的外墙安装控制线,保证外墙安装的精确度;电站双面叠合剪力墙的墙板吊装采用吊装梁,根据预制墙板的吊环位置设置合理的起吊点,用卸扣将钢丝绳与外墙板的预留吊环通过卸扣连接后,起吊至距地500mm处,检查构件外观质量及吊环连接无误后继续起吊。起吊前500mm宽的通长多层板钉制于需将预制墙板下侧,匀速起吊,以确保不损坏预制墙板边缘,有效避免了变电站双面叠合剪力墙的外墙安装的精确度不足以及变电站双面叠合剪力墙的预制墙板边缘容易受损的缺陷。
Construction method for double-sided laminated shear wall of transformer substation
According to the construction method for the double-sided laminated shear wall of the transformer substation, an outer wall positioning line of the double-sided laminated shear wall of the transformer substation is paid off according to the axis relation on a construction drawing of the double-sided laminated shear wall of the transformer substation, and meanwhile, an outer wall installation control line of the double-sided laminated shear wall of the transformer substation is paid off to ensure the accuracy of outer wall installation; a hoisting beam is adopted for hoisting the wallboard of the power station double-sided laminated shear wall, a reasonable hoisting point is arranged according to the position of a hoisting ring of the prefabricated wallboard, after a steel wire rope and a reserved hoisting ring of an outer wallboard are connected through a shackle, the wallboard is hoisted to the position 500 mm away from the ground, and hoisting continues after the appearance quality of a component and the correct connection of the hoisting ring are checked. Before hoisting, the full-length multi-layer board with the width of 500 mm is nailed on the lower side of the prefabricated wallboard to be hoisted at a constant speed, so that it is ensured that the edge of the prefabricated wallboard is not damaged, and the defects that the installation accuracy of the outer wall of the double-sided laminated shear wall of the transformer substation is insufficient and the edge of the prefabricated wallboard of the double-sided laminated shear wall of the transformer substation is prone to being damaged are effectively overcome.
一种针对变电站双面叠合剪力墙的施工方法,根据变电站双面叠合剪力墙的施工图纸上的轴线关系放出变电站双面叠合剪力墙的外墙定位线,同时放出变电站双面叠合剪力墙的外墙安装控制线,保证外墙安装的精确度;电站双面叠合剪力墙的墙板吊装采用吊装梁,根据预制墙板的吊环位置设置合理的起吊点,用卸扣将钢丝绳与外墙板的预留吊环通过卸扣连接后,起吊至距地500mm处,检查构件外观质量及吊环连接无误后继续起吊。起吊前500mm宽的通长多层板钉制于需将预制墙板下侧,匀速起吊,以确保不损坏预制墙板边缘,有效避免了变电站双面叠合剪力墙的外墙安装的精确度不足以及变电站双面叠合剪力墙的预制墙板边缘容易受损的缺陷。
Construction method for double-sided laminated shear wall of transformer substation
一种针对变电站双面叠合剪力墙的施工方法
ZHOU YUELIN (Autor:in) / FAN YANWEI (Autor:in) / NA YU (Autor:in) / QIU ZHIBIN (Autor:in) / ZHANG YIQUAN (Autor:in) / YAO LIANGLIANG (Autor:in) / XU XIAOFEI (Autor:in) / WU XUPENG (Autor:in) / BIAN LIHUA (Autor:in) / ZHENG ZICHEN (Autor:in)
29.11.2024
Patent
Elektronische Ressource
Chinesisch
Steel plate truss double-sided laminated shear wall and construction method thereof
Europäisches Patentamt | 2021
|Prefabricated rib plate double-sided laminated shear wall
Europäisches Patentamt | 2024
|Separating type combined double-sided laminated shear wall
Europäisches Patentamt | 2024
|Scribing device for construction of double-sided laminated shear wall and using method
Europäisches Patentamt | 2023
|