Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Rock area wind tower combined foundation
The invention relates to the technical field of wind tower foundations, in particular to a combined foundation of a wind tower in a rock area. Comprising an original foundation, a top table is arranged at the top of the original foundation, a first hidden beam is annularly arranged on the periphery of the top table, a plurality of anchor bolts are annularly arranged on the first hidden beam, and the anchor bolts are anchored into the original foundation; a new foundation is poured on the side face of the original foundation and connected with the original foundation and the first hidden beams through steel bars. Second hidden beams are arranged on the periphery of the original foundation in the circumferential direction, a plurality of prestress assemblies are evenly arranged on the second hidden beams, and the lower portions of the prestress assemblies are anchored into the rock soil layer. The combined foundation is improved on the basis of an original foundation, the service life of the original foundation and facilities is prolonged, resource utilization is achieved to a large extent, various problems existing in an existing technical method are comprehensively solved, and technical guarantee is provided for obtaining and implementing a future wind power upgrading and rebuilding project.
本发明涉及风塔基础技术领域,尤其是涉及一种岩石地区风塔组合式基础。包括原有基础,原有基础的顶部设有顶台,顶台周边环向设有第一暗梁,第一暗梁环向设有多个锚栓,锚栓锚入所述原有基础内部;原有基础的侧面浇筑有新基础,新基础通过钢筋与原有基础及第一暗梁连接;原有基础周边环向设有第二暗梁,第二暗梁上均匀设有多个预应力组合件,预应力组合件的下部锚入岩石土层中。本发明提供的组合式基础在原有基础上进行改进,较大限度的为原有基础及设施进行延寿和资源化利用,综合解决现有技术方法中存在的各种问题,为未来风电升级改造项目的获取和项目的实施提供技术保障。
Rock area wind tower combined foundation
The invention relates to the technical field of wind tower foundations, in particular to a combined foundation of a wind tower in a rock area. Comprising an original foundation, a top table is arranged at the top of the original foundation, a first hidden beam is annularly arranged on the periphery of the top table, a plurality of anchor bolts are annularly arranged on the first hidden beam, and the anchor bolts are anchored into the original foundation; a new foundation is poured on the side face of the original foundation and connected with the original foundation and the first hidden beams through steel bars. Second hidden beams are arranged on the periphery of the original foundation in the circumferential direction, a plurality of prestress assemblies are evenly arranged on the second hidden beams, and the lower portions of the prestress assemblies are anchored into the rock soil layer. The combined foundation is improved on the basis of an original foundation, the service life of the original foundation and facilities is prolonged, resource utilization is achieved to a large extent, various problems existing in an existing technical method are comprehensively solved, and technical guarantee is provided for obtaining and implementing a future wind power upgrading and rebuilding project.
本发明涉及风塔基础技术领域,尤其是涉及一种岩石地区风塔组合式基础。包括原有基础,原有基础的顶部设有顶台,顶台周边环向设有第一暗梁,第一暗梁环向设有多个锚栓,锚栓锚入所述原有基础内部;原有基础的侧面浇筑有新基础,新基础通过钢筋与原有基础及第一暗梁连接;原有基础周边环向设有第二暗梁,第二暗梁上均匀设有多个预应力组合件,预应力组合件的下部锚入岩石土层中。本发明提供的组合式基础在原有基础上进行改进,较大限度的为原有基础及设施进行延寿和资源化利用,综合解决现有技术方法中存在的各种问题,为未来风电升级改造项目的获取和项目的实施提供技术保障。
Rock area wind tower combined foundation
一种岩石地区风塔组合式基础
CAO DONG (Autor:in) / ZHU LIMING (Autor:in) / LIU CHUNDONG (Autor:in)
03.12.2024
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2024
|