Method for building traffic tunnel, pipeline tunnel or pressure water tunnel in tuba building mode
The invention relates to a method for constructing a traffic tunnel, a pipe tunnel or a pressurized water tunnel in a tubule construction manner, in which tubule members (10) are assembled in a machine-produced bore in a rock or soil layer to form a closed lining in the form of a tubule, and an annular gap between the bore and the outer wall of the tubule is filled with a composition, in which the tubule members (10) are connected to the tubule members (10) and the tubule members (10) and the tubule members (10) are connected to the tubule members (10). The present invention relates to a composition comprising a reaction resin cured by polymerization and a filler, the filler being fed to the reaction resin cured by polymerization before or during transport into the annular gap, the reaction resin being mixed with the filler and dispersed in the filler, characterized in that the composition is free of cement, and in that the composition is free of cement. And the filler comprises an inorganic material that does not react with water, the inorganic material having an average particle size of < = 500 [mu] m.
本发明涉及一种以丘宾筒建造方式建造交通隧道、管道隧道或压力水隧道的方法,其中将丘宾筒构件(10)在岩石或土层中的由机器产生的孔中组装,以构成丘宾筒管形式的封闭衬砌,并且对在孔与丘宾筒管的外壁之间的环形间隙填充组合物,该组合物包含通过聚合固化的反应树脂和填料,其中填料在输送到环形间隙中之前或期间被供给所述通过聚合固化的反应树脂,该反应树脂与填料混匀并且分散在填料中,其特征在于:所述组合物不含水泥,并且填料包含不与水发生反应的无机材料,该无机材料具有≤500μm的平均粒度。
Method for building traffic tunnel, pipeline tunnel or pressure water tunnel in tuba building mode
The invention relates to a method for constructing a traffic tunnel, a pipe tunnel or a pressurized water tunnel in a tubule construction manner, in which tubule members (10) are assembled in a machine-produced bore in a rock or soil layer to form a closed lining in the form of a tubule, and an annular gap between the bore and the outer wall of the tubule is filled with a composition, in which the tubule members (10) are connected to the tubule members (10) and the tubule members (10) and the tubule members (10) are connected to the tubule members (10). The present invention relates to a composition comprising a reaction resin cured by polymerization and a filler, the filler being fed to the reaction resin cured by polymerization before or during transport into the annular gap, the reaction resin being mixed with the filler and dispersed in the filler, characterized in that the composition is free of cement, and in that the composition is free of cement. And the filler comprises an inorganic material that does not react with water, the inorganic material having an average particle size of < = 500 [mu] m.
本发明涉及一种以丘宾筒建造方式建造交通隧道、管道隧道或压力水隧道的方法,其中将丘宾筒构件(10)在岩石或土层中的由机器产生的孔中组装,以构成丘宾筒管形式的封闭衬砌,并且对在孔与丘宾筒管的外壁之间的环形间隙填充组合物,该组合物包含通过聚合固化的反应树脂和填料,其中填料在输送到环形间隙中之前或期间被供给所述通过聚合固化的反应树脂,该反应树脂与填料混匀并且分散在填料中,其特征在于:所述组合物不含水泥,并且填料包含不与水发生反应的无机材料,该无机材料具有≤500μm的平均粒度。
Method for building traffic tunnel, pipeline tunnel or pressure water tunnel in tuba building mode
以丘宾筒建造方式建造交通隧道、管道隧道或压力水隧道的方法
TINTELNOT GARY (Autor:in)
13.12.2024
Patent
Elektronische Ressource
Chinesisch
Online Contents | 1996
|Engineering Index Backfile | 1909
|Difficulties of tunnel building
Engineering Index Backfile | 1892
|Building Baltimore's big tunnel
Engineering Index Backfile | 1940
|Building tunnel under Mont Blanc
Engineering Index Backfile | 1964
|