Reinforced concrete cast-in-situ bored pile construction process
The invention relates to the field of foundation pit construction, in particular to a reinforced concrete cast-in-situ bored pile construction technology which comprises the steps that S1, a steel sleeve is embedded; the bottom end of the steel sleeve is arranged on the top of a constructed cast-in-place pile in a sleeving mode, and the top end of the steel sleeve is fixedly installed on the ground. S2, sediment located at the top of the constructed cast-in-place pile is removed; s3, discharging the slurry in the drill hole; s4, concrete is poured into the drill holes; and S5, the steel sleeve is pulled out from the underground. The method has the effect that when concrete pouring of the cast-in-place pile is discontinuous, the negative influence of pile breaking is reduced so as to ensure the safety inside and outside the foundation pit.
本申请涉及基坑施工领域,尤其涉及一种钢筋混凝土钻孔灌注桩施工工艺,其包括S1、埋设钢套筒;所述钢套筒的底端套设于已施工灌注桩的顶部,所述钢套筒的顶端固定安装于地面;S2、清除位于所述已施工灌注桩顶部的沉渣;S3、排出钻孔内的泥浆;S4、向所述钻孔内灌注混凝土;S5、将所述钢套筒自地下拔出。本申请具有在灌注桩的混凝土灌注不连续时,减少断桩的负面影响以确保基坑内和基坑外的安全的效果。
Reinforced concrete cast-in-situ bored pile construction process
The invention relates to the field of foundation pit construction, in particular to a reinforced concrete cast-in-situ bored pile construction technology which comprises the steps that S1, a steel sleeve is embedded; the bottom end of the steel sleeve is arranged on the top of a constructed cast-in-place pile in a sleeving mode, and the top end of the steel sleeve is fixedly installed on the ground. S2, sediment located at the top of the constructed cast-in-place pile is removed; s3, discharging the slurry in the drill hole; s4, concrete is poured into the drill holes; and S5, the steel sleeve is pulled out from the underground. The method has the effect that when concrete pouring of the cast-in-place pile is discontinuous, the negative influence of pile breaking is reduced so as to ensure the safety inside and outside the foundation pit.
本申请涉及基坑施工领域,尤其涉及一种钢筋混凝土钻孔灌注桩施工工艺,其包括S1、埋设钢套筒;所述钢套筒的底端套设于已施工灌注桩的顶部,所述钢套筒的顶端固定安装于地面;S2、清除位于所述已施工灌注桩顶部的沉渣;S3、排出钻孔内的泥浆;S4、向所述钻孔内灌注混凝土;S5、将所述钢套筒自地下拔出。本申请具有在灌注桩的混凝土灌注不连续时,减少断桩的负面影响以确保基坑内和基坑外的安全的效果。
Reinforced concrete cast-in-situ bored pile construction process
一种钢筋混凝土钻孔灌注桩施工工艺
YU HUIFEN (Autor:in) / YANG YANMEI (Autor:in) / XU SIYI (Autor:in)
17.12.2024
Patent
Elektronische Ressource
Chinesisch
Drilling tool for reinforced concrete cast-in-situ bored pile
Europäisches Patentamt | 2023
|Pile foundation construction process of cast-in-situ bored pile
Europäisches Patentamt | 2024
|Pile foundation construction process of cast-in-situ bored pile
Europäisches Patentamt | 2023
|