The invention discloses a reinforcing and repairing construction method for an existing damaged cave in a loess area, belongs to the technical field of building construction, and solves the problem that a traditional brick ring reinforcing method cannot guarantee the stability of a cave crown soil body and the safety of construction operation. The method comprises the following steps: mounting a detachable movable back-jacking support in the cave dwelling, covering soil on the top of the cave dwelling, cleaning the surface of the cave dwelling and solidifying, reinforcing an anchor rod soil body, reinforcing a brick lining voucher, constructing a kiln face, constructing an inner decorative surface and constructing a drainage structure at the top of the cave dwelling. According to the method disclosed by the invention, the upper soil body is solidified by adopting the flexible anchor rods and the reinforcing mesh through the detachable movable back-jacking support, the resistance to a humid environment is improved by adopting the stone-built arch feet, the one-roll one-volt retreating method is used for building and is effectively tied with the kiln face, the stress is reasonable, and the integrity of the cave dwelling is ensured.
本发明公开了一种黄土地区既有残损窑洞加固与修复施工方法,属于建筑施工技术领域,解决了传统砖圈加固法无法保证窑顶土体稳固性及施工作业安全性的问题。本发明方法包括步骤:在窑洞内安装可拆卸移动式回顶支撑、窑顶覆土清表及固化、锚杆土体加固施工、砖衬券加固施工、窑脸施工、内饰面施工和窑洞顶部的排水结构的施工。本发明方法通过可拆卸移动式回顶支撑,采用柔性锚杆+钢筋网对上部土体固结,石砌拱脚提升其对潮湿环境的抵抗性,一卷一伏的退槎法砌筑与窑脸有效拉结,受力合理,保证了窑洞的整体性。
Construction method for reinforcing and repairing existing damaged cave dwelling in loess area
The invention discloses a reinforcing and repairing construction method for an existing damaged cave in a loess area, belongs to the technical field of building construction, and solves the problem that a traditional brick ring reinforcing method cannot guarantee the stability of a cave crown soil body and the safety of construction operation. The method comprises the following steps: mounting a detachable movable back-jacking support in the cave dwelling, covering soil on the top of the cave dwelling, cleaning the surface of the cave dwelling and solidifying, reinforcing an anchor rod soil body, reinforcing a brick lining voucher, constructing a kiln face, constructing an inner decorative surface and constructing a drainage structure at the top of the cave dwelling. According to the method disclosed by the invention, the upper soil body is solidified by adopting the flexible anchor rods and the reinforcing mesh through the detachable movable back-jacking support, the resistance to a humid environment is improved by adopting the stone-built arch feet, the one-roll one-volt retreating method is used for building and is effectively tied with the kiln face, the stress is reasonable, and the integrity of the cave dwelling is ensured.
本发明公开了一种黄土地区既有残损窑洞加固与修复施工方法,属于建筑施工技术领域,解决了传统砖圈加固法无法保证窑顶土体稳固性及施工作业安全性的问题。本发明方法包括步骤:在窑洞内安装可拆卸移动式回顶支撑、窑顶覆土清表及固化、锚杆土体加固施工、砖衬券加固施工、窑脸施工、内饰面施工和窑洞顶部的排水结构的施工。本发明方法通过可拆卸移动式回顶支撑,采用柔性锚杆+钢筋网对上部土体固结,石砌拱脚提升其对潮湿环境的抵抗性,一卷一伏的退槎法砌筑与窑脸有效拉结,受力合理,保证了窑洞的整体性。
Construction method for reinforcing and repairing existing damaged cave dwelling in loess area
黄土地区既有残损窑洞加固与修复施工方法
REN SHENGXUE (Autor:in) / XUE JIANXIONG (Autor:in) / LI JUREN (Autor:in) / ZHAO YONGMAO (Autor:in) / CAO LILI (Autor:in) / NIE LIANG (Autor:in) / LIU JIANBIN (Autor:in) / HE JINGFENG (Autor:in) / WANG MEILIAN (Autor:in) / JIANG SHAN (Autor:in)
17.12.2024
Patent
Elektronische Ressource
Chinesisch
Reinforcing structure of cave dwelling and reinforcing method thereof
Europäisches Patentamt | 2024
|Shield-like loess cave dwelling tunneling work station
Europäisches Patentamt | 2023
|