Waterproof structure of horizontal construction joint of basement outer wall stiff column and construction method of waterproof structure
The invention relates to the technical field of building construction, and discloses a waterproof structure of a horizontal construction joint of a basement outer wall stiff column and a construction method thereof, the waterproof structure comprises a foundation beam, a pre-poured concrete layer arranged at the top of the foundation beam, and a post-poured concrete layer arranged at the top of the pre-poured concrete layer; the structure is characterized in that a basement outer wall stiff column is arranged in the post-pouring concrete layer, the basement outer wall stiff column and the pre-pouring concrete layer are arranged at intervals, a mounting plate is arranged at the bottom of the basement outer wall stiff column, a plurality of leveling bolts are arranged in the foundation beam, leveling nuts are arranged on the leveling bolts, and the leveling bolts are connected with the mounting plate. The tops of the multiple leveling bolts penetrate through the mounting plate, and a waterproof component is arranged between the mounting plate and the pre-cast concrete layer.
本发明涉及建筑施工技术领域,公开了一种地下室外墙劲性柱水平施工缝的防水结构及其施工方法,包括:基础梁,设置于所述基础梁顶部的先浇混凝土层,以及设置于所述先浇混凝土层顶部的后浇混凝土层;其特征在于,所述后浇混凝土层内设置有地下室外墙劲性柱,所述地下室外墙劲性柱和先浇混凝土层间隔设置,地下室外墙劲性柱的底部设置有安装板,所述基础梁内设置有多个调平螺栓,多个所述调平螺栓上设置有调平螺母,多个所述调平螺栓的顶部穿过安装板,安装板和先浇混凝土层之间设置有防水构件。
Waterproof structure of horizontal construction joint of basement outer wall stiff column and construction method of waterproof structure
The invention relates to the technical field of building construction, and discloses a waterproof structure of a horizontal construction joint of a basement outer wall stiff column and a construction method thereof, the waterproof structure comprises a foundation beam, a pre-poured concrete layer arranged at the top of the foundation beam, and a post-poured concrete layer arranged at the top of the pre-poured concrete layer; the structure is characterized in that a basement outer wall stiff column is arranged in the post-pouring concrete layer, the basement outer wall stiff column and the pre-pouring concrete layer are arranged at intervals, a mounting plate is arranged at the bottom of the basement outer wall stiff column, a plurality of leveling bolts are arranged in the foundation beam, leveling nuts are arranged on the leveling bolts, and the leveling bolts are connected with the mounting plate. The tops of the multiple leveling bolts penetrate through the mounting plate, and a waterproof component is arranged between the mounting plate and the pre-cast concrete layer.
本发明涉及建筑施工技术领域,公开了一种地下室外墙劲性柱水平施工缝的防水结构及其施工方法,包括:基础梁,设置于所述基础梁顶部的先浇混凝土层,以及设置于所述先浇混凝土层顶部的后浇混凝土层;其特征在于,所述后浇混凝土层内设置有地下室外墙劲性柱,所述地下室外墙劲性柱和先浇混凝土层间隔设置,地下室外墙劲性柱的底部设置有安装板,所述基础梁内设置有多个调平螺栓,多个所述调平螺栓上设置有调平螺母,多个所述调平螺栓的顶部穿过安装板,安装板和先浇混凝土层之间设置有防水构件。
Waterproof structure of horizontal construction joint of basement outer wall stiff column and construction method of waterproof structure
一种地下室外墙劲性柱水平施工缝的防水结构及其施工方法
WANG SHAOFEI (Autor:in) / SHI YUTONG (Autor:in) / YAN SHUAI (Autor:in) / TAO HONGXING (Autor:in) / ZHAO ZHIBING (Autor:in) / SUN JIANFU (Autor:in)
31.12.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Basement outer wall construction joint waterproof structure and construction method
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Basement outer wall waterproof structure and construction method thereof
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2024
|