Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
PILE FOUNDATION AND TOWER RECONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a pile foundation reducing the construction cost by increasing breaking strength of a beam while reducing the size thereof, and to provide a tower reconstruction method capable of reducing the construction cost by suppressing expansion of site for newly building a tower in place of an existing tower as well as expansion of the cost for buying a site therefor.SOLUTION: Disclosed pile foundation 100 is a pile foundation which includes: beam parts 120a to 120d for supporting main leg materials (10a to 10d) of a steel-tower; and a pile part 110 which is built in the center thereof. Each of the main leg materials includes: plural pressure bearing plates 130 attached to a part disposed within the beam; and a helical reinforcement bar 150 or a ring reinforcement which is lied enclosing the main leg material within the beam.SELECTED DRAWING: Figure 2
【課題】破壊強度を高めることで梁を小型化することができ、建設コストを削減することが可能な杭基礎、ならびに既設鉄塔を建て替える際の用地の拡大およびそれに起因する用地の買い増しを抑制することにより建設コストの削減を図ることが可能な鉄塔建替工法を提供することを目的とする。【解決手段】本発明にかかる杭基礎100の構成は、鉄塔の各主脚材(10a〜10d)を支持する梁部120a〜120dと、その中央に構築された杭部110とを含む杭基礎において、主脚材のうち梁部内に配置される部分に取り付けられる複数の支圧板130と、梁部内で主脚材を取り囲むように巻回された螺旋鉄筋150またはリング鉄筋と、を備えることを特徴とする。【選択図】図2
PILE FOUNDATION AND TOWER RECONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a pile foundation reducing the construction cost by increasing breaking strength of a beam while reducing the size thereof, and to provide a tower reconstruction method capable of reducing the construction cost by suppressing expansion of site for newly building a tower in place of an existing tower as well as expansion of the cost for buying a site therefor.SOLUTION: Disclosed pile foundation 100 is a pile foundation which includes: beam parts 120a to 120d for supporting main leg materials (10a to 10d) of a steel-tower; and a pile part 110 which is built in the center thereof. Each of the main leg materials includes: plural pressure bearing plates 130 attached to a part disposed within the beam; and a helical reinforcement bar 150 or a ring reinforcement which is lied enclosing the main leg material within the beam.SELECTED DRAWING: Figure 2
【課題】破壊強度を高めることで梁を小型化することができ、建設コストを削減することが可能な杭基礎、ならびに既設鉄塔を建て替える際の用地の拡大およびそれに起因する用地の買い増しを抑制することにより建設コストの削減を図ることが可能な鉄塔建替工法を提供することを目的とする。【解決手段】本発明にかかる杭基礎100の構成は、鉄塔の各主脚材(10a〜10d)を支持する梁部120a〜120dと、その中央に構築された杭部110とを含む杭基礎において、主脚材のうち梁部内に配置される部分に取り付けられる複数の支圧板130と、梁部内で主脚材を取り囲むように巻回された螺旋鉄筋150またはリング鉄筋と、を備えることを特徴とする。【選択図】図2
PILE FOUNDATION AND TOWER RECONSTRUCTION METHOD
杭基礎および鉄塔建替工法
WADA SHUJI (Autor:in) / SAITO DAICHI (Autor:in) / HIRONAKA SATORU (Autor:in) / TANABE SHIGERU (Autor:in)
08.02.2018
Patent
Elektronische Ressource
Japanisch
Europäisches Patentamt | 2023
|Tower pile foundation of power transmission line and construction method of tower pile foundation
Europäisches Patentamt | 2022
|