Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
INSTALLATION METHOD OF TEMPORARY SUPPORT COLUMN
To provide an installation method of a temporary support column allowing the temporary support column to be easily installed through being adjoined to a boundary of a site with relation to a public road when installing the temporary support column configured to support a temporary structure and like at a construction site.SOLUTION: A head of a core member 2 projecting on a site ground is configured as a temporary support column 7 by erecting the core member 2 in a way that the head is above the ground with relation to an earth retaining pile 1 in order to construct the earth retaining pile 1 at an installation position of the temporary support column 7 for an earth retaining pile construction to construct the earth retaining pile 1 in a foundation G.SELECTED DRAWING: Figure 2
【課題】建設工事現場において仮設構造物等を支持するための仮設支柱を設置するにあたり、公道に対する敷地内の境界部に近接させて当該仮設支柱を簡単に設置可能な技術を提供する。【解決手段】地盤Gに山留杭1を構築する山留杭構築工事において、仮設支柱7の設置箇所に山留杭1を構築するにあたり、当該山留杭1に対して芯材2を頭部が地上に突出する状態で建て込み、当該地上に突出した芯材2の頭部を仮設支柱7とする。【選択図】図2
INSTALLATION METHOD OF TEMPORARY SUPPORT COLUMN
To provide an installation method of a temporary support column allowing the temporary support column to be easily installed through being adjoined to a boundary of a site with relation to a public road when installing the temporary support column configured to support a temporary structure and like at a construction site.SOLUTION: A head of a core member 2 projecting on a site ground is configured as a temporary support column 7 by erecting the core member 2 in a way that the head is above the ground with relation to an earth retaining pile 1 in order to construct the earth retaining pile 1 at an installation position of the temporary support column 7 for an earth retaining pile construction to construct the earth retaining pile 1 in a foundation G.SELECTED DRAWING: Figure 2
【課題】建設工事現場において仮設構造物等を支持するための仮設支柱を設置するにあたり、公道に対する敷地内の境界部に近接させて当該仮設支柱を簡単に設置可能な技術を提供する。【解決手段】地盤Gに山留杭1を構築する山留杭構築工事において、仮設支柱7の設置箇所に山留杭1を構築するにあたり、当該山留杭1に対して芯材2を頭部が地上に突出する状態で建て込み、当該地上に突出した芯材2の頭部を仮設支柱7とする。【選択図】図2
INSTALLATION METHOD OF TEMPORARY SUPPORT COLUMN
仮設支柱の設置方法
SAEGUSA DAISUKE ( Autor:in ) / KAWAGUCHI HIROSHI ( Autor:in )
22.03.2019
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
TEMPORARY COLUMN AND INSTALLATION METHOD FOR THE SAME
Europäisches Patentamt | 2016
|Temporary support system and installation method of AAC board
Europäisches Patentamt | 2025
|